Non-National Highway System pavement projects

Hwy DOT Metro District

Scoring criteria for non-national highway system pavement projects. Out of 100 possible points, 60 points are based on the timing of the improvement, 10 points are based on traffic volume, 10 points are based on truck volume, 10 points are based on other infrastructure needs, 5 points are based on the potential to transfer jurisdiction of the road to a city or county, and 5 points are based on the miles covered by the project.

Learn more about how Hwy DOT evaluates and selects pavement projects

Hwy DOT scores stretches of highway based on a pavement need when selecting projects to include in the 10-year Capital Highway Investment Plan. Pavement needs on the National Highway System (NHS) are scored and selected separately from pavement needs off the system. Hwy DOT’s approach to managing pavements follows the guidance and targets in the Transportation Asset Management Plan and the planned outcomes in Hwy SHIP.

Pavement projects are scored and selected within each district. Potential pavement projects are identified by the Highway Pavement Management Application (HPMA) and by Hwy DOT District staff.

Once selected, Hwy DOT then identifies and evaluates alternatives and other needs, legal requirements, issues and opportunities in coordination with local partners, and considers public input. In the process, non-pavement work may be added to a pavement project or a pavement project may be combined with a nearby bridge project. The department follows a context-sensitive complete streets approach, which considers the needs of all users. The final project may address a substantial number of needs beyond the pavement need that precipitated the project. Projects may move years based on local coordination, project delivery, timing of other nearby construction projects, and funding shifts.

What was selected

Related links

How the projects scored

The construction costs shown on this list represent a very rough estimate based on limited information available at the time selection decisions were made. Actual construction and delivery costs will change over time as projects go from a concept through the project development process and are eventually constructed. View more detailed scores (Excel).

Last updated October 2023

Score Route Description High level construction cost estimate for planning purposes Year Planned (FY) Comments
13.5 Hwy 284 Resurface Hwy 284 from 122nd Street to Sparrow Road.   $6,862,524   2031  
15 Hwy 56 Resurface road from the Goodhue/Dakota County line to Hwy 50/US 52    $7,252,392   2033 Projected poor pavement conditions. 2020 RSL 4 to 11 years. 
18 Hwy 77 Resurface Hwy 77 (Cedar) from 138th St (CR 23) to the Dakota-Hennepin County line in Apple Valley    $45,096,000   2026, 2027   Poor pavement conditions. 
21 Hwy 20 Resurface road from Hwy 19 to Hwy 50    $5,000,000   2032 Poor pavement conditions. 2020 RSL 2 to 10 years.
21 Hwy 95 Resurface Hwy 95 from Jct Hwy 8 to Hwy 97.   $15,000,000   2032  
24 Hwy 5 Resurface road from County Rd 11 to Hwy 41   $5,000,000   2032 Projected poor pavement conditions.
25 Hwy 51 Resurface road from W 7th to Dayton Ave    $10,099,747   2030 Poor pavement conditions.
27 Hwy 13 Medium mill and overlay from Connelly Pkwy to old Hwy 101 $2,000,000 Not selected Program limited by available funding.
27 Hwy 13 Medium mill and overlay from Hwy 13 to Hwy 149 $200,000 Not selected Program limited by available funding.
29 US61 Medium mill and overlay from 267th St to I35 $300,000 Not selected Program limited by available funding.
29 Hwy 65 Medium mill and overlay from south of E Moore Lake Dr to Anoka County Road 10 $3,100,000 Not Selected  Program limited by available funding.
31 Hwy 7 Repair road from W end of 494 bridge. to I-494    $500,000   2032 Poor pavement conditions.
32 US61 Medium mill and overlay from RP155 to 170th ST $200,000 Not selected Program limited by available funding.
33 US61 Resurface road from 3rd St. to US 10    $6,250,000   2032 Poor pavement conditions.
34 US61 Resurface road and repair bridge 19075 on Hwy 61 from N Jct Hwy 316 to 4th St in Hastings   $10,867,000   2027   Poor pavement conditions. 
35 Hwy 97 Reconstruct road, trail on Hwy 97 (Scandia Trail N) from 0.24 miles east of I-35/Hwy 61 (Forest Blvd N) and add turn lanes and lighting on Hwy 97 (Scandia Trail N) from west of Everton Ave N to Hwy 61 (Forest Blvd N) in Forest Lake    $15,884,000   2025   Geometrics. Poor pavement conditions. Ped/bike trail needs. 
39 Hwy 97 Minor rehabilitation within roundabout at US61 100000 Not selected Newer concrete roundabouts.
40 Hwy 13 Medium mill and overlay from Washburn Ave to I-35 $1,400,000 Not Selected  Program limited by available funding.
43 Hwy 13 Reconstruct road from Eagle Creek Ave to County Rd 42 $3,500,000 Not selected Projected poor pavement conditions.
43 Hwy 5 Medium mill and overlay from I-494 to Hennepin/Ramsey County line $3,900,000 Not Selected  Program limited by available funding.
43 Hwy 65 Repair road from 217th Ave to Anoka-Isanti County line $18,000,000 Not Selected  Repair early distresses.
44 Hwy 95 Medium mill and overlay from I-94 to .5 miles S of I-94 $500,000 Not selected Program limited by available funding.
46 Hwy 101 Repair and resurface road, update guardrail and median barrier, signal replacement, ADA curb ramps, drainage, turn lane extension and pork chop island realignment on Hwy 101 from I-94 in Rogers to CR 38 (70th St NE) in Otsego    $12,674,000   2027   Poor pavement conditions. 
47 Hwy 19 Resurface road from the Leseuer/Scott county line to the Scott/Rice county line - Future Project $2,700,000 Not selected  
47 Hwy 95 Thin mill and overlay from I-94 to Mulberry St 18000000 Not selected Projected poor pavement conditions. 2020 RSL is 4 to 6 years.
55 Hwy 5 Medium mill and overlay from Carver County Road 10 to Oak Ave $200,000 Not selected Program limited by available funding.
55 Hwy 121 Medium mill and overlay from I35W to Pedestrian bridge $300,000 Not Selected  Program limited by available funding.
57 Hwy 149 Medium mill and overlay from I-494 to Mendota Heights Rd $600,000 Not selected Program limited by available funding.
57 Hwy 50 Medium mill and overlay from Hwy 3 to US52 $4,300,000 Not selected Program limited by available funding.
57 US61 Medium mill and overlay from RP163 to 250TH St $200,000 Not selected Program limited by available funding.
58 Hwy 149 Medium mill and overlay from Mendota Heights Rd to Hwy 5/7th St 2500000 Not selected Program limited by available funding.
59 Hwy 5 Medium mill and overlay from Hwy 25 to Carver  County Road 10 $1,900,000 Not selected Program limited by available funding.
60 Hwy 77 Medium mill and overlay from Minnesota River bridge to I-494 $3,100,000 Not Selected  Program limited by available funding.
60 Hwy 5 Repair road from Hwy 41 to Eden Prairie Rd   $16,609,000   2033 Much of this is older PCC with ride impacted by isolated crack slabs, some of which are from subsurface utility issues.
61 Hwy 95 Medium mill and overlay from Valley Creek to Bailey Rd 1200000 Not selected Program limited by available funding.
61 Hwy 101 Minor concrete pavement repair, from CR 38 to US 10 $3,500,000 Not Selected  Poor pavement conditions. 
62 Hwy 243 Medium mill and overlay from Hwy 95 to St Croix River $700,000 Not selected Program limited by available funding.
62 Hwy 95 Medium mill and overlay from I-94 to Valley Creek 700000 Not selected Program limited by available funding.
63 US61 Medium mill and overlay from 70th St to Carver Ave $4,400,000 Not Selected  Program limited by available funding.
63 US61 Medium mill and overlay from Trailer Pk entrance to 170th St  $1,000,000 Not selected Program limited by available funding.
64 Hwy 149 Medium mill and overlay from Albano Tr to Hwy 55 $2,600,000 Not selected Program limited by available funding.
64 Hwy 95 Medium mill and overlay from Bailey Rd to US61 4100000 Not selected Program limited by available funding.
64 Hwy 95 Medium mill and overlay from Sunrise River to Taylors Falls $6,600,000 Not selected Program limited by available funding.
64 US61 Medium mill and overlay from 170th St to Hwy 97 $1,900,000 Not selected Program limited by available funding.
65 Hwy 13 Medium mill and overlay from Dakota County Line to Washburn Ave $700,000 Not Selected  Program limited by available funding.
65 Hwy 5 Medium mill and overlay from .2 miles W of Carver County Road 10 to .2 miles east of Carver County Road 10 $200,000 Not selected Program limited by available funding.
66 Hwy 7 Medium mill and overlay from I-494 to Shady Oak Road 1000000 Not Selected  Program limited by available funding.
66 Hwy 95 Medium mill and overlay from St Croix Trail to Point Rd 1000000 Not selected Program limited by available funding.
66 Hwy 13 Medium mill and overlay from .4 miles west of Dakota Ave to .2 miles east of Dakota ave $700,000 Not Selected  Program limited by available funding.
67 Hwy 7 Medium mill and overlay from Railroad bridge to Hwy 100 $900,000 Not Selected  Program limited by available funding.
67 US61 Medium mill and overlay from Chisago County Road 31/22 to 267th St  $200,000 Not selected Program limited by available funding.
67 US61 Medium mill and overlay from I-94/Mounds Blvd to Hwy 5/7th St $700,000 Not selected Program limited by available funding.
68 Hwy 95 Medium mill and overlay from Mulberry to St Saint Croix Trail $500,000 Not selected Program limited by available funding.
68 US61 Medium mill and overlay from 250th St to Chisago County Road 31/32 $700,000 Not selected Program limited by available funding.
68 US61 Medium mill and overlay from White Bear Lake Cr to Frenchman Rd $1,800,000 Not selected Program limited by available funding.
68 Hwy 13 Medium mill and overlay from Hwy 282 to Scott County Road 21 roundabout $2,000,000 Not selected Program limited by available funding.
68 Hwy 65 Medium mill and overlay from 26th St to 10th ST $1,300,000 Not Selected  Program limited by available funding.
68 Hwy 101 Medium mill and overlay from NB split with US169 to SB merge with US169  $3,400,000 Not Selected  Program limited by available funding.
69 Hwy 149 Medium mill and overlay from Hwy 3 to Albano Tr $200,000 Not selected Program limited by available funding.
69 US61 Medium mill and overlay from Frenchman Rd to Trailer Pk entrance $400,000 Not selected Program limited by available funding.
69 Hwy 3 Resurface road from 145th St to Hwy 149   $4,622,021   2033  
69 Hwy 5 Medium mill and overlay from Birch St to Scandia Rd $1,100,000 Not selected Program limited by available funding.
70 Hwy 51 Resurface road and ADA improvements on Hwy 51 (Snelling Ave) from Grand Ave to St Clair Ave in St Paul    $2,183,000   2024   Poor pavement conditions. 
70 Hwy 65 Resurface road from NE 37th Ave CL to 53rd Ave NE    $5,270,000   2033 Projected poor pavement conditions.
70 Hwy 101 Resurface road from Hwy 5 (W 78th St) to CSAH 62/Townline Rd, resurface road, drainage repairs and ADA improvements on Hwy 101 (W 192nd Ave) from Hwy 5 to Townline Rd in Chanhassen/Eden Prairie    $1,887,000   2024   Poor pavement conditions. 
71 Hwy 13 Medium mill and overlay from Yankee Doodle Rd to I494 $900,000 Not selected RQI does not match on the ground conditions
71 Hwy 3 Medium mill and overlay from Hwy 149 to Bridge 19045 $1,300,000 Not selected Program limited by available funding. 2020 Remaining service life 0 to 7 years. Short PCC section driving down Remaining service life.
72 Hwy 7 Resurface road from TH 25 to Carver County Line    $10,522,000   2033 Projected poor pavement conditions.
72 Hwy 95 Medium mill and overlay from Point Rd to I-94 $2,800,000 Not selected RQI does not match on the ground conditions
72 US61 Medium mill and overlay from US 10 to 70th St $8,500,000 Not Selected  Program limited by available funding.
72 US61 Medium mill and overlay from Hwy 96 to White Bear Lake CL $1,000,000 Not selected RQI does not match on the ground conditions
72 Hwy 13 Medium mill and overlay from Dakota to Washburn ave $1,600,000 Not Selected  Program limited by available funding.
72 Hwy 3 Reconstruct the road from Amana Trail to Hwy 62   $10,400,000   2033  
73 Hwy 7 Medium mill and overlay from Texas Ave to Railroad Bridge  700000 Not Selected  RQI does not reflect on the ground conditions
73 Hwy 13 Medium mill and overlay legs to and from Scott County Road 21 roundabout $300,000 Not selected Very new pavement either side of new roundabout.
73 Hwy 21 Medium mill and overlay from 7th St to Sawmill Rd $4,300,000 Not selected RQI does not match on the ground conditions
73 Hwy 3 Medium mill and overlay from Bridge 19045 to Mendota Rd $500,000 Not selected RQI does not match on the ground conditions
74 Hwy 284 Reconstruct road from US 212 to 122nd St   $4,480,000   2031 Many issues with this pavement including geometric and ADA needs. RQI data not reflective of the poor pavement conditions.
74 Hwy 51 Medium mill and overlay from Grey Fox Rd to I694 $300,000 Not selected Recently repaired in 2021
74 Hwy 13 Medium mill and overlay from Hwy 13 to Dakota Ave $700,000 Not Selected  Program limited by available funding.
76 Hwy 50 Resurface Hwy 50 (240th St) from Hwy 52 (Emery Ave/Rochester Blvd) in Hampton to Hwy 61 in Douglas Township   $7,196,000   2026   Poor pavement conditions. 
76 Hwy 21 Medium mill and overlay from Sawmill Rd to Mill St $300,000 Not selected RQI does not match on the ground conditions
77 Hwy 120 Resurface Hwy 120 from BrookView Dr to 4th St.   $2,112,476   2032 Projected poor pavement conditions.
77 Hwy 21 Medium mill and overlay from Hwy 19 to Scott County Road 37 $300,000 Not selected Program limited by available funding. Short urban section.
77 Hwy 3 Resurface road from Rice County line to Hwy 50    $10,207,680   2029 Poor pavement conditions. 
78 Hwy 7 Medium mill and overlay from Shady Oak Rd to Texas Ave $3,000,000 Not Selected  RQI does not reflect on the ground conditions
78 Hwy 13 Medium mill and overlay from  Scott County Road 42 to Connelly Pkwy $700,000 Not selected RQI does not match on the ground conditions
78 Hwy 3 Medium mill and overlay from Hwy 50 to Dakota County Road 58 $3,300,000 Not selected Program limited by available funding. 2020 Remaining service life is predicted 9 to 15 years.
78 Hwy 65 Repair pavement and replace bridges 6817 ( new bridge # 02X06) and 9417 (02X07) over Coon Creek, replace box culvert bridge 9465 and ADA, signal replacement on Hwy 65 (Central Ave) from CR 10 (Mounds View Blvd) in Spring Lake Park to 217th Ave in East Bethel, cable median barrier from Bunker Lake Blvd to 237th    $40,546,000   2024   Poor pavement conditions. 
78 Hwy 65 Resurface road form 53rd Ave NE to South Moore Lake Dr $3,000,000 Not Selected  Poor pavement conditions.
79 Hwy 51 Resurface, guardrail and ADA on Hwy 51 (Snelling Ave N) from north end of bridge over Hwy 36 in Roseville to 0.1 mile north of Grey Fox Rd in Arden Hills   $6,678,000   2026   Poor pavement conditions. ADA, bike/ped, and drainage needs. 
79 Hwy 96 Resurface road from US 61 to Hwy 95 $10,280,000 Not selected Projected poor pavement conditions.
81 Hwy 7 Resurface road from the Hennepin/Carver County line to Division St and replace bridge over County Road 82.   $31,280,000   2029 Recent resurfacing project. Construction in progress at time of DIV run. Roughness at intersection contribute to poor ride.
81 Hwy 97 Resurface road from US61 to Hwy 95   $8,957,692   2032 Poor pavement conditions. Project has been deferred several times. 
81 US61 Thin mill and overlay from Goodhue/Dakota County Line to Hwy 316 $9,000,000 Not Selected Projected poor pavement conditions.
81 Hwy 5 Medium mill and overlay from Hennepin/Ramsey County Line to Munster Ave $600,000 Not selected Not selected. Program limited by available funding. Short section of PCC before and after river bridge. Bridge surface is pulling average RQI down.
82 US61 Resurface road, traffic signals, pedestrian improvements, drainage, curb and gutter and replace bridge #96093 on Hwy 61 from 0.2 miles north of Carver Ave to east junction of I-94 in St Paul.   $10,000,000   2028 Poor pavement conditions.
87 Hwy 95 Resurface Hwy 95 from Hemingway Ave to Manning Bridge over Sunrise River.   $7,009,720   2031 Poor pavement conditions. 2020 RSL 0 to 5 years.
90 Hwy 95 Resurface Hwy 95 from the Isanti county line to Hemingway Ave    $9,002,400   2028  
90 Hwy 95 Resurface road from Hwy 97 to Hwy 36   $13,000,000   2030 Projected poor pavement conditions.
90 Hwy 13 Medium mill and overlay from I-35W to Yankee Doodle Rd $6,900,000 Not selected RQI does not match on the ground conditions
61 Hwy 101 Minor concrete pavement repair, from CR 38 to US 10 $3,500,000 Not Selected  Poor pavement conditions. 