Central Minnesota

2025 work

These roadwork projects on state highways will have traffic impacts, but will be led, constructed and communicated by the city, township or county. Check 511mn.org for current impacts on these projects.

Update drainage

Replace drainage structures at Hwy 371 and Design Rd. in Baxter

Construct roundabout

Update and improve access at the intersection with a new roundabout at Business Hwy 371 (S Sixth St.) and Willow St. in Brainerd, Crow Wing County (city led)

Improve access

Project location
Sherburne County will improve access along Hwy 10 between St. Cloud and Clear Lake. Select map for larger image (PNG)

Sherburne County to update access and improve safety along Hwy 10, between St. Cloud and Clear Lake, Haven Township, includes the accesses to/from Co. Rd. 65, 7 and 61.

  • Projects are as follows:
    1. COMPLETE June-July 2025: Reconfigure access on Hwy 10 at Co. Rd. 61 (47th St. SE) with a right in/out design; includes an acceleration lane
    2. COMPLETE early August-mid-October, 2025: Update access on Hwy 10 at Co. Rd. 65 (42nd St. SE) and Co. Rd. 7 (45th Ave. SE) with a J-turn design
  • Construct: 2025
  • Impacts: Lane or shoulder closures on Hwy 10; local access changes/detours, follow road signs
  • Estimated cost: $3 million
  • Led by: Sherburne County

 

Improve access

Construct right turn-lane on Hwy 25 to 14th St NE in Buffalo

  • Construct: 2025
  • Impacts: Lane or shoulder closure on Hwy 25; local access changes to 14th St. NE
  • Estimated cost: $200,000
  • Led by: City of Buffalo

 

2026 work

These roadwork projects on state highways will have traffic impacts, but will be led, constructed and communicated by the city, township or county. Check 511mn.org for current impacts on these projects.

Sherburne County to construct new interchange 2025-2026

Construct new interchange at Hwy 169 and Co. Rd. 4 (Freemont Ave.) in Zimmerman.

  • Construct: August 2025-November 2026
    • Local roads and preparation work in 2026
    • Hwy 169 and local roads in 2027
  • Impacts: Lane closures, changes to access on Hwy 169 and local roads in Zimmerman.
  • Led by: Sherburne County
Project location
Sherburne County to construct a new interchange at Zimmerman at Hwy 169 and Co. Rd. 4 in 2025-2026. Hwy 169 impacts at future interchange in 2026. Select work map image (JPG) to enlarge. Image by Sherburne County.

Improve access and traffic flow

Wright County to construct a roundabout at Hwy 25 and Co. Rd. 113. The project will be coordinated with MnDOT's 2026 roadwork project on Hwy 25 from Buffalo to Monticello.

  • Construct: July-late fall 2026
  • Impacts: Lane or shoulder closure on Hwy 25; local access changes to 14th St. NE
  • Estimated cost: TBD
  • Led by: Wright County

Wright County to improve access at interchange

Construct roundabouts at the I-94 interchange on/off ramps and Co. Rd. 137.

  • Construct: 2026
  • Impacts: lane closures, changes to access, follow directional signs. I-94 impacts will be shared through the I-94 Gap project
  • Estimated cost: $5.8 million
  • Led by: Wright County
Project location
Wright County Co. Rd. 137 project location map of two-year project on Co. Rd. 137 in Albertville and Otsego. Select map for larger image (PNG). Map by Wright County.