Hwy 12 Litchfield to Cokato project update: Road from Darwin to Dassel set to reopen today, Oct. 2
WILLMAR, Minn. – The two-year Hwy 12 resurfacing and concrete repair project between Litchfield and Cokato is making significant progress. MnDOT announces that Phase 2 of the project is set to be completed today, with plans to reopen the road from Darwin to Dassel this afternoon, Wednesday, October 2.
Looking ahead, Phase 3, which includes Hwy 12 from Dassel to Cokato, is scheduled for construction in 2025. This phase will involve:
- Concrete repairs and replacement of asphalt shoulders from east of Hwy 15 in Dassel to the end of the concrete section in Cokato.
- Upgrades to sidewalks and pedestrian ramps in Dassel to meet ADA standards.
- Improvements to ramps along the trail from Dassel to Cokato to ensure ADA compliance.
Project benefits and cost
Benefits of the project include a smoother road surface, improved drainage, and enhanced safety for people who walk and bike. Duininck, Inc., is the contractor, and the project cost is approximately $11.3 million.
Stay connected, informed
- Learn more about the Hwy 12 project to Litchfield to Cokato.
###