Hwy 30 resurfacing completed between Stewartville and Chatfield
STEWARTVILLE, Minn. – Highway 30 resurfacing is completed between Stewartville and Chatfield, according to the Minnesota Department of Transportation.
The work started July 15 and was completed in October. During that time, crews:
- Resurfaced 15 miles of Hwy 30 from 5th Avenue NE in Stewartville to Mill Creek Road in Chatfield.
- Constructed 6-foot-wide shoulders from Maplebrook Drive NE to 15th Avenue NE in Stewartville.
- Made accessibility improvements from Maplebrook Drive NE to 12 Avenue NE in Stewartville.
- Installed new lighting at Olmsted County Road 1.
- Made culvert improvements.
To learn more about this project, go to MnDOT’s website.
Stay connected, informed
- Check out other MnDOT southeast Minnesota construction projects and sign up for construction updates.
###