I-90 resurfacing, bridge replacement

Nodine to Dakota

About this project

Summary of work

MnDOT is planning a resurfacing and bridge replacement project on I-90 between Nodine and Dakota in Winona County. Construction is scheduled to begin May 4, 2026. Work is expected to be completed in November.

The following is the planned work on I-90 from Nodine to Dakota in Winona County.

I-90 Nodine Hills map
I-90 project map
  • Repave 5 miles of westbound and 4.7 miles of eastbound I-90.
  • Replace the westbound I-90 bridge over Winona Co. Rd. 101.
  • Replace approach panels and bridge barrier guardrail connections on the westbound I-90 bridge over southbound Hwy 61.
  • Improve safety by providing a slight banking of the right lane of northbound I-90 approaching the bridge over southbound Hwy 61.
  • Install new guardrail on the eastbound and westbound lanes and improve drainage.
  • Install a reinforcement and a synthetic liner to reduce sinkhole risks associated with Karst geology.
  • Clean and reestablish rock catchment areas.

Traffic impacts

During construction, the following impacts will occur.

  • Single lane traffic during paving and bridge work, delays are expected.
  • Winona County Road 101 will be closed and detoured during the work, which begins mid-May. The county road detour is expected to be several months at a time as crews replace the bridge half at a time, while keeping one I-90 lane open. The County Road 101 detour route is: Winona County Road 12 west at Dakota to Dakota Valley Drive east.