Concrete Pavement Rehabilitation
- Review  the following:
              
- CPR Standards Details, 2302 Standard specification (Spec book), Special Provisions, Plans, and Schedule of Materials Control (SMC.) If needed, Contact the MnDOT Concrete Engineering Unit for clarification.
 - Attend the pre-construction meeting if possible.
 
 
- View the CPR guide.
 
- Marking Repairs:
 - Have Contractor set up a lane closure at least 1 day in advance of beginning CPR work.
 - Check soundness of concrete pavement with hammer, sand, and/or chain drag.
 - Use paint to mark the areas that require repair work.
 
- Pavement Removal:
 - Ensure the erosion control devices are in place before any concrete sawing commences.
 - The pavement needs to be swept with a pickup broom on a regular basis.
 
-  Verify all materials are certified and  approved.  
              
- Check the approved products lists on the Approved/Qualified Products website.
 
 - Partial Depth Repairs (Type B):
 - Check all Type B repairs to make sure the deteriorated concrete is removed.
 - Check repairs are sandblasted clean and are clear of laitance and oils.
 - Assure the bonding grout does not whiten (dries) after application in Type B repairs. If the bonding grout whitens reject the repair and re-sandblasting of the repair.
 - Before concrete placement, ensure the compression relief material (joint filler) and / or joint reestablishment material (wax coated cardboard) is in place.
 - To prevent reflective cracking, place joint filler between the repair and the adjacent lane.
 - If needed perform gradation tests on the 3U18 aggregate.
 
- Full Depth Repairs (Type C):
 - Verify the base is level with the bottom of the pavement and compacted. Additions to / removal of in place base material is common.
 - Check for proper installation of dowel bars by requiring an adhesive anchoring test section.
 - The specification requires the installation dowel bars and then cores are taken in order to check the adequacy of the adhesive surrounding dowel bars.
 
- Dowel Bar Retrofit (DBR):
 - Make sure the bottoms of the slots are flat and sandblasted clean.
 - Ensure the crack / joint caulked completely. If the DBR backfill material infiltrates into the crack / joint a compression spalls will likely occur.
 
- Placement and Finishing:
 - Ensure proper consolidation (vibration) of the concrete.
 - Refer to the specification for straightedge tolerances. Check the repairs as often as necessary to ensure smoothness.
 - It is good practice to finish Type B repairs from the middle of the repair to the outside of the repair.
 
- Curing:
              
- Review current curing requirements.
 - Verify an approved curing compound is used from the Approved/Qualified Products website.
 - Check application rate of curing compound for uniformity, yield, and timely placement.
 - Ensure compliance with rain and cold weather protection requirements.
 
 - Perform  all required sampling and testing in accordance with Schedule of Materials  Control. 
              
- When the concrete is not pumped, perform air content and slump testing at the point of placement. If the concrete is pumped, take sample at the point of delivery.
 - If there is any question about the consistency or the quality of the concrete, run additional tests as necessary.
 -    Notify Contractor and truck driver if air  content or slump results are outside of Specifications.
 
 - Compressive  Strength Testing (Cylinders):
              
- Check the Schedule of Materials Control for sampling rates.
 - Make and store cylinders where they are protected from vibration or disturbance until placed in the curing tank.
 - Provide protection from extreme variations in temperature from the time of casting cylinder until it is transported to the lab.
 - Make additional control cylinders as necessary. Cure control cylinders in the same manner as the repair.
 
 
- Collect  and initial all Certificate of Compliances (Batch Tickets):  
              
- Verify  all the information printed on the Certificate of Compliance is correct: 
                  
- Verify S.P. Number
 - Verify Mix Number
 - Verify delivery time is within Specifications
 - Verify Water – Total Actual Water vs. Mix Design Water
 - Verify whether or not water is allowed to be added
 - Record any additional water that was added at the job site.
 - Verify Mn/DOT Certified Plant I Technician representing the Producer signed the first Certificate of Compliance for each mix type, each day.
 
 
 - Verify  all the information printed on the Certificate of Compliance is correct: 
                  
 
- Check repairs for failures:
 - All CPR repairs have a warranty period, it is essential the repairs are checked for failures before the warranty time period expires.
 
- Maintain  daily diary:
              
- Includes hours, equipment, concrete temperatures, air content, slump reading, cylinder data, stations paved, width, depth, yield, weather, air temperatures, and problems or unique circumstances encountered.
 
 - Field Documentation:
 - Document all 3U18 field test results in the CPR Workbook
 - Submit both to the Concrete Engineering Unit on a weekly basis
 
References: Mn/DOT Standard Specifications for Construction, Contract Plans and Special Provisions, Schedule of Materials Control and Mn/DOT Concrete Manual.
