Highway 5/East 7th Street and Highway 61/Arcade Street

St. Paul and Maplewood

Meet with the project team in-person on Thursdays in April. Bring your questions, comments and concerns directly to the project team. For more information, visit the meetings webpage.

This webpage is not updated over the weekend/overnight. For up-to-date information on traffic impacts, visit 511mn.org.

Traffic impacts

East 7th Street and Arcade Street in Saint Paul and Maplewood project location map

East 7th St. and Arcade St. project area map

View full-size map

All traffic impacts are tentative and weather dependent. Local access to residences and businesses will be maintained. Expect increased noise and vibration during construction. Prepare for potential changes to your typical route and parking access.

Upcoming

Information about upcoming traffic impacts will be posted as details become available. Drivers can expect intermittent intersection closures throughout the project area; however, no two consecutive intersections will be closed at the same time. Vehicles will be able to make left turns only at specific intersections during construction. People walking and rolling can expect sidewalks and boulevards to be removed and reconstructed during the project, please follow the posted detours for any closures.

Road closures

Mon, April 6 through fall
  • Arcade St. is closed in both directions between Neid Ln. and East 7th St.

Lane closures

Mon, April 6 through summer
  • East 7th St. is reduced to one lane in both directions between Minnehaha Ave. and Mounds Blvd.
    • Local access to residences and businesses will be maintained

Construction timeline

East 7th Street and Arcade Street closure and restrictions map

East 7th St. and Arcade St. closure and restrictions map

View full-size map

  • Arcade St. between Neid Ln. and East 7th St.: Spring through fall 2026
  • East 7th St. between Minnehaha Ave. and Mounds Blvd.: Spring through summer 2026
  • East 7th St. between Minnehaha Ave. and I-94: Summer through fall 2026

Construction activities

Crews will remove and replace existing sidewalks, roadway surfaces, traffic signals, and bus stops throughout the project area. Utility work (water, electrical, gas, etc.) will occur intermittently throughout all parts of the project area, not just where road construction is happening.

About this project

In March 2025, we began the two-year reconstruction project along East 7th St., and Arcade St. between I-94 in St. Paul and Roselawn Ave. in Maplewood. Construction on East 7th St. will occur during the 2026 construction season. When complete, the new roadway will improve traffic flow, decrease traffic delays and improve safety on the road.

Summary of work

  • Resurfacing the road
  • Repairing sidewalks
  • Updating sidewalk curb ramps and driveways
  • Updating and improving pedestrian lighting
  • Updating and improving traffic signals
  • Updating and improving bus stops