Highway 169 and Highway 282/County Road 9

Jordan

This webpage is not updated over the weekend/overnight. For up-to-date information on traffic impacts, visit 511mn.org.

Traffic impacts

Intersection of Hwy 169 and Hwy 282/Co. Rd. 9 in Jordan project location map

Hwy 169 and Hwy 282 in Jordan project location map

View full-size map

All traffic impacts are tentative and weather dependent. Syndicate St. to/from Hwy 169 is permanently closed.

Current

Road closures

7 p.m. Sun, May 4 through mid-July
9 p.m. Wed, April 30 through fall
  • Creek Ln. to/from Hwy 169 is closed

Lane closures

Through mid-July
  • Co. Rd. 9 is reduced to one lane in both directions between Ervin Industrial Dr. and Hwy 169
5 a.m. Tue, April 15 through late November
  • Hwy 169 is reduced to one lane in both directions between Hwy 282 and Hwy 21

Access changes

5 a.m. Tue, July 1

Upcoming

Information about upcoming traffic impacts will be posted as details become available.

About this project

We are partnering with the city of Jordan and Scott County on a project which will include a new Hwy 169 and Hwy 282/Co. Rd. 9 interchange, two bridges (over Hwy 169 and railroad tracks), two roundabouts, pedestrian tunnel, sidewalks, retaining walls, and noise walls.

Summary of work

  • Construct new interchange at Hwy 169 and Hwy 282/Co. Rd. 9
  • Build roundabout at the Co. Rd. 9 and Syndicate St. intersection
  • Build roundabout at the Co. Rd. 9 and 190th St./Valley View Dr. intersection
  • Build Co. Rd. 9 bridge over Union Pacific railroad tracks
  • Widen and repair Hwy 169 bridge over Sand Creek
  • Add traffic signal at NB Hwy 169 exit ramp and Hwy 282
  • Build pedestrian tunnel under Hwy 169 and add new trail connections
  • Construct Hwy 169 acceleration and deceleration lanes
  • Build stormwater improvements
  • Create retaining walls along various areas of the project
  • Add noise walls on both sides of Hwy 169, north of Syndicate St. and Creek Lane

Project timeline

The following tentative traffic impacts are anticipated and subject to change:

Intersection of Hwy 169 and Hwy 282/Co. Rd. 9 in Jordan project staging map

Hwy 169 and Hwy 282 in Jordan project staging map

View full-size map

Stage 1: Spring to early summer 2025

  • Work begins on Hwy 169 interchange
  • Single-lane Hwy 169 traffic in each direction

Stage 2: Summer to fall 2025

  • Single-lane Hwy 169 traffic in each direction
  • Roundabout construction at Co. Rd. 9 and Valley View Dr.
  • Co. Rd. 9 remains open
  • Alternating detour for 190th St./Valley View Dr.
  • Construct pedestrian underpass

Stage 3: 2026

  • Work on Hwy 282/Co. Rd. 9 overpass
  • Single-lane Hwy 169 traffic in each direction
  • Occasional overnight closures of Hwy 169 for bridge work
  • Temporary traffic light at Hwy 169 and Creek Ln.
  • Truck traffic exiting and entering Hwy 169 at Co. Rd. 9 will instead be detoured to Delaware Ave./Co. Rd. 59

Stage 4: 2027

  • Median and finishing work on Hwy 169
  • Single-lane Hwy 169 traffic in each direction
  • Remove temporary traffic light at Hwy 169 and Creek Ln.
  • Hwy 282/Co. Rd. 9 overpass opens to traffic