Non-National Highway System pavement projects
MnDOT District 7
MnDOT scores stretches of highway based on a pavement need when selecting projects to include in the 10-year Capital Highway Investment Plan. Pavement needs on the National Highway System (NHS) are scored and selected separately from pavement needs off the system. MnDOT’s approach to managing pavements follows the guidance and targets in the Transportation Asset Management Plan and the planned outcomes in MN SHIP.
Pavement projects are scored and selected within each district. Potential pavement projects are identified by the Highway Pavement Management Application (HPMA) and by MnDOT District staff.
Once selected, MnDOT then identifies and evaluates alternatives and other needs, legal requirements, issues and opportunities in coordination with local partners, and considers public input. In the process, non-pavement work may be added to a pavement project or a pavement project may be combined with a nearby bridge project. The department follows a context-sensitive complete streets approach, which considers the needs of all users. The final project may address a substantial number of needs beyond the pavement need that precipitated the project. Projects may move years based on local coordination, project delivery, timing of other nearby construction projects, and funding shifts.
What was selected
Related links
- District 7 project selection
- District 7 National Highway System pavement projects
- District 7 Urban pavement projects
How the projects scored
The construction costs shown on this list represent a very rough estimate based on limited information available at the time selection decisions were made. Actual construction and delivery costs will change over time as projects go from a concept through the project development process and are eventually constructed.
Last updated November 2024
Score | Route | Description | High Level Cost Estimate for Planning Purposes | Year Planned (FY) | Comments |
90 | US Hwy 75 | Resurface from Luverne to Trosky; replace 3 bridges | $10,300,000 | 2028, Future | 6705-47 |
87 | Hwy 15 | Resurface from Iowa to Fairmont | $5,200,000 | Not Selected | 4603-52; Not a district priority, will continue to monitor pavement performance |
85 | Hwy 19 | Resurface from Gaylord to Henderson | $20,200,000 | 2030 | 7206-117 |
85 | Hwy 19 | Resurface from Hwy 169 to east Jct of Hwy 13 | $17,900,000 | 2032 | 4004-126 |
85 | Hwy 22 | Medium mill and overlay from Sunrise Dr in St. Peter to Nicollet County Road 20 | $5,300,000 | Not Selected | Will be completed with remainder of the Hwy 22 to US 169 in St. Peter |
85 | Hwy 22 | Reconstruction from Hungry Hollow Rd to Maple Hill Rd | $1,500,000 | Not Selected | Not a district priority, will continue to monitor pavement performance |
84 | Hwy 13 | Resurface from Waterville to Montgomery | $15,100,000 | 2031 | 4001-48 |
83 | Hwy 86 | Resurface Hwy 86 from I-90 to Hwy 60 (Except Lakefield); replace or improve drainage; replace signs | $4,600,000 | Not Selected | 3208-1101745; Not a district priority, will continue to monitor pavement performance |
83 | Hwy 68 | Reclaim and overlay from Hwy 15 south of New Ulm to US Hwy 169 | $14,800,000 | 2031 | 0710-123 |
82 | Hwy 19 | Medium mill and overlay from Red Wing Ave to Leroy Ave | $800,000 | Not Selected | Not a district priority, will continue to monitor pavement performance |
81 | Hwy 4 | Resurface Hwy 4 from Martin Hwy 26 near Sherburn to Hwy 60 near St. James; replace 1 bridge and repair 3 bridges | $21,954,637 | 2025, Prior | 4602-27 |
80 | Hwy 13 | Resurface from Montgomery to New Prague | $6,520,000 | 2034 | 4002-1071423 |
80 | Hwy 22 | Medium mill and overlay from 6th Ave NE to Blue Earth County Road 15 | $5,500,000 | Not Selected | NA |
80 | Hwy 22 | Medium mill and overlay from County Road 90 to Hungry Hollow Rd | $300,000 | Not Selected | NA |
79 | Hwy 22 | Resurface from Iowa border to west Jct of CR 16 | $8,400,000 | 2033 | 2203-115 |
79 | Hwy 22 | Resurface from west Jct of CR 16 to Wells | $6,500,000 | 2029 | 2204-27 |
79 | Hwy 30 | Resurface Hwy 30 from US 71 to Darfur; replace or improve drainage, signing and lighting | $6,100,000 | Not Selected | 1702-1101744 |
79 | Hwy 5 | Cold in place recycling and medium overlay from Hwy 22 to east of 4th St in Arlington | $3,700,000 | Not Selected | NA |
78 | Hwy 5 | Cold in place recycling and medium overlay from 5th St to US 212 | $3,100,000 | Not Selected | NA |
78 | Hwy 91 | Resurface Hwy 91 from Iowa to Adrian | $8,000,000 | Not Selected | 5307-1112064 |
77 | Hwy 99 | Medium mill and overlay from east side of railroad crossing east of St. Peter to Maple Avenue in Le Center | $6,300,000 | Not Selected | NA |
76 | Hwy 19 | Resurface Hwy 19 from Fairfax to Gibbon | $6,500,000 | Not Selected | 7204-1112109 |
76 | Hwy 93 | Medium mill and overlay from Minnesota River Bridge to US Hwy 169 | $400,000 | Not Selected | NA |
76 | US Hwy 75 | Resurface from Iowa border to Luverne | $9,900,000 | 2033 | 6704-116 |
75 | Hwy 22 | Medium mill and overlay from Maple Hill Road to Hwy 86 | $400,000 | Not Selected | NA |
74 | Hwy 13 | Medium mill and overlay from 2.2 miles north of Hwy 30 to 1.5 miles north of Waseca | $4,100,000 | Not Selected | NA |
74 | Hwy 22 | Resurface Hwy 22 from Gaylord to Hwy 212; replace bridge 72003 and rehab bridge 72004; replace or improve drainage, signing and lighting | $4,800,000 | Not Selected | 7208-1101723 |
73 | Hwy 19 | Medium mill and overlay from 11th Ave SW to New Prague western City Limits | $200,000 | Not Selected | NA |
72 | Hwy 19 | Resurface Henderson to Hwy 169 | $2,000,000 | 2031 | 7206-1121943 |
72 | Hwy 257 | Resurface from Hanska to Hwy 15 | $2,000,000 | Not Selected | 0808-1038067 |
72 | Hwy 83 | Reclaim and overlay from Blue Earth County Road 173 to Blue Earth County Road 41 | $7,200,000 | Not Selected | NA |
71 | Hwy 109 | Hwy 109 from east side of Winnebago to western Wells limits | $7,300,000 | Not Selected | NA |
71 | Hwy 19 | Resurface from Winthrop to Gaylord | $8,800,000 | 2029 | 7205-118 |
71 | Hwy 22 | Reconstruct from Hwy 83 to Bassett Dr | $16,500,000 | 2032 | 0704-1069603 |
71 | Hwy 22 | Unbonded overlay from north of Blue Earth County Road 15 to north junction of Blue Earth County Road 90 | $3,400,000 | Not Selected | NA |
71 | Hwy 264 | Resurface from Round Lake to I-90 | $2,600,000 | 2029 | 5310-13 |
71 | Hwy 68 | Medium mill and overlay from County Road 4 in Morgan to Hwy 4 in Sleepy Eye | $4,000,000 | Not Selected | NA |
70 | Hwy 13 | Medium mill and overlay from Hwy 30 to 2.2 miles north of Hwy 30 | $1,200,000 | Not Selected | NA |
70 | Hwy 22 | Medium mill and overlay from .3 miles north of Blue Earth County Road 90 to .6 miles north of Blue Earth County Road 90 | $300,000 | Not Selected | NA |
70 | Hwy 22 | Medium mill and overlay from .33 south of Hwy 83 to 200ft north of Hwy 83 | $400,000 | Not Selected | NA |
70 | Hwy 83 | Thick mill and overlay from 1000ft east of Blue Earth County Road 41 to 1000ft west of Blue Earth County Road 41 | $300,000 | Not Selected | NA |
68 | Hwy 30 | Medium mill and overlay from 1 mile east of US Hwy 169 to Troendle St NW | $5,200,000 | Not Selected | NA |
68 | Hwy 4 | Medium mill and overlay from Iowa/Minnesota Border to County Road 26 (where Hwy 4 turns right) | $5,200,000 | Not Selected | NA |
68 | Hwy 4 | Medium mill and overlay from Hwy 68 to Hwy 19 in Fairfax | $4,300,000 | Not Selected | NA |
68 | Hwy 83 | Medium mill and overlay from Hwy 30 to Blue Earth County Road 173 | $6,900,000 | Not Selected | NA |
67 | Hwy 19 | Medium mill and overlay from Alton Ave to Red Wing Ave | $200,000 | Not Selected | NA |
65 | Hwy 22 | Medium mill and overlay from 1500 south of the west junction US Hwy 212 to US Hwy 212 | $200,000 | Not Selected | NA |
64 | Hwy 99 | Medium mill and overlay from Hwy 13 to Hwy 21 | $4,100,000 | Not Selected | NA |
61 | Hwy 109 | Medium mill and overlay from Hwy 22 to I-90 | $5,200,000 | Not Selected | NA |
61 | US59 | Medium mill and overlay from the Iowa/Minnesota Border to Hwy 60 | $2,200,000 | Not Selected | NA |
60 | Hwy 5 | Medium mill and overlay from Sibley County Road 15 to 5th St | $300,000 | Not Selected | NA |
60 | Hwy 83 | Reclaim and overlay from Blue Earth County Road 41 to Ichabod Lane | $300,000 | Not Selected | NA |
54 | Hwy 4 | Reclaim and overlay from 3rd Ave SW in Sleepy Eye to Hwy 68 | $2,000,000 | Not Selected | NA |
53 | Hwy 19 | Minor CPR and diamond grinding from Hwy 4 to Hwy 15 | $5,000,000 | Not Selected | NA |
46 | Hwy 13 | Resurface from Waseca to Waterville | $5,700,000 | 2033 | 8102-30 |
43 | Hwy 13 | Thin mill and overlay from Waseca County Road 103 to 5th St in Waseca | $500,000 | Not Selected | NA |
43 | Hwy 62 | Medium mill and overlay from US/59 Fulda City limits to Plum Ave in Windom | $12,300,000 | Not Selected | NA |
41 | Hwy 111 | Thin mill and overlay from US 14 to Seventh Street in Nicollet | $200,000 | Not Selected | NA |
41 | Hwy 30 | Resurface from Hwy 15 to Hwy 169 | $6,000,000 | 2033 | 0705-26 |
41 | Hwy 5 | Medium mill and overlay from 4th Ave E to Blue Earth County Road 15 | $2,900,000 | Not Selected | NA |
40 | Hwy 13 | Medium mill and overlay from 1.5 miles south of Waseca to .728 miles north of Waseca County Road 103 | $500,000 | Not Selected | NA |
40 | Hwy 83 | Thin mill and overlay from Ichabod Lane to Hwy 22/Victory Dr | $100,000 | Not Selected | NA |
27 | Hwy 22 | Resurface Hwy 22 from St Peter to Hwy 111; pedestrian improvements | $5,800,000 | 2027 | 5205-113 |
23 | Hwy 91 | Medium mill and overlay from I-90 to Murray County line | $3,900,000 | Not Selected | NA |
20 | Hwy 30 | Cold in place recycling from Hwy 83 to western New Richland city limits | $4,900,000 | Not Selected | NA |
19 | Hwy 22 | Reclaim and overlay from Hwy 111 to Sibley County Road 67 | $7,400,000 | Not Selected | NA |
18 | Hwy 13 | Minor CPR and diamond grinding from .2 miles south of Hwy 60 to .26 miles north of Hwy 60 | $200,000 | Not Selected | NA |
18 | Hwy 19 | Thin mill and overlay from Le Sueur County Road 143 to 11th Ave SW | $200,000 | Not Selected | NA |
16 | Hwy 4 | Minot CPR and diamond grinding from Hwy 60 to Wantonwan County Road 12 | $200,000 | Not Selected | NA |