National Highway System pavement projects
MnDOT District 2
MnDOT scores stretches of highway based on a pavement need when selecting projects to include in the 10-year Capital Highway Investment Plan. Pavement needs on the National Highway System (NHS) are scored and selected separately from pavement needs off the system. MnDOT’s approach to managing pavements follows the guidance and targets in the Transportation Asset Management Plan and the planned outcomes in MnSHIP.
Pavement projects are scored and selected within each district. Potential pavement projects are identified by the Highway Pavement Management Application (HPMA) and by MnDOT District staff.
Once selected, MnDOT then identifies and evaluates alternatives and other needs, legal requirements, issues and opportunities in coordination with local partners, and considers public input. In the process, non-pavement work may be added to a pavement project or a pavement project may be combined with a nearby bridge project. The department follows a context-sensitive complete streets approach, which considers the needs of all users. The final project may address a substantial number of needs beyond the pavement need that precipitated the project. Projects may move years based on local coordination, project delivery, timing of other nearby construction projects and funding shifts.
What was selected
Related links
- District 2 project selection
- District 2 Non-National Highway System pavement projects
- District 2 Urban pavement projects
How the projects scored
The construction costs shown on this list represent a very rough estimate based on limited information available at the time selection decisions were made. Actual construction and delivery costs will change over time as projects go from a concept through the project development process and are eventually constructed.
Last updated November 2024
Score | Route | Description | High Level Cost Estimate for Planning Purposes | Year Planned (FY) | Comments |
100 | US Hwy 2 | Resurface Hwy 2, east bound and west bound lanes in Cass Lake | $677,606 | 2024 | 1102-75 |
88 | US Hwy 2 | Resurface Hwy 2, westbound lane from Shevlin to Wilton | $5,500,000 | 2033 | 0406-1101143 |
84 | US Hwy 2 | Resurface the eastbound lanes of Hwy 2 between East Grand Forks and Fisher | $7,300,000 | 2034 | 6001-1038994 Scored in 2019 |
80 | Hwy 371 | Recondition Hwy 371 between Hackensack and Hwy 200 | $6,500,000 | Not Selected | Coordinating funding with another district |
80 | US Hwy 2 | Resurface westbound lanes of Hwy 2 between Fosston and Bagley | $16,000,000 | 2033 | 6005-80 Scored in 2019 |
77 | Hwy 11 | Resurface Hwy 11 from Karlstad to Kittson/Roseau County line | $6,500,000 | 2034 | 3503-1101187 |
77 | US Hwy 2 | Resurface Hwy 2 between Wilton and Bemidji | $2,800,000 | Not Selected | 0406-1038659 Scored in 2019 |
77 | US Hwy 59 | Resurface Hwy 59 between Hwy 2 and Brooks and replace a box culvert near Brooks | $8,000,000 | 2032 | 6009-1073503 Scored in 2019 |
75 | Hwy 11 | Resurface Hwy 11 between Hwy /ND border and Karlstad | $9,700,000 | Not Selected | District does not expect pavement segment to deteriorate as fast as model predicts |
75 | US Hwy 2 | Resurface westbound lanes of Hwy 2 between Hwy 59 and Fosston | $4,200,000 | 2029 | 6005-79 Scored in 2019 |
75 | US Hwy 2 | Resurface westbound lanes of Hwy 2 between Polk County Road 44 and Hwy 32 | $3,600,000 | Not Selected | 2020 Construction. Not a district priority, will continue to monitor pavement performance |
74 | US Hwy 71 | Resurface Hwy 71 from Movil Lake Road to CR 23/CR 21 in Turtle River | $7,200,000 | 2034 | 0410-54 Scored in 2019 |
73 | Hwy 11 | Resurface Hwy 11 between west of CR 2 in Williams to CR 61 east of Williams | $3,200,000 | 2028 | 3901-44 |
71 | US Hwy 2 | Resurface Hwy 2 between the Cass CO line and Itasca County Road 18 | $6,800,000 | Not Selected | 2020 Construction Not a district priority, will continue to monitor pavement performance |
70 | US Hwy 2 | Resurface Hwy 2 between Hwy 75 and Groveland Ave in Crookston | $5,000,000 | 2029 | 6002-83 |
70 | US Hwy 2 | Resurface eastbound lanes of Hwy 2 between Fosston and Bagley | $14,000,000 | 2034 | 6005-69 Scored in 2019 |
70 | US Hwy 71 | Resurface Hwy 71 between Turtle River and Tenstrike | $9,700,000 | 2026 | 0410-51 Scored in 2019 |
70 | US Hwy 71 | Resurface Hwy 71 from Tenstrike to Blackduck and resurface one mile of Hwy 72 north of Blackduck | $9,600,000 | 2028 | 0410-53 |
69 | Hwy 11 | Resurface Hwy 11 between Warroad and Roosevelt and replace three box culverts | $16,200,000 | 2028 | 6804-28 |
68 | Hwy 371 | Resurface Hwy 371 between Walker and Cass Lake | $14,150,000 | Not Selected | 1120-1073343 Scored in 2020 |
68 | Hwy 371 | Resurface Hwy 371 from Steamboat River Bridge to Cass Lake | $14,200,000 | 2033 | 1120-1123303 |
67 | US Hwy 2 | Resurface westbound lanes of Hwy 2 between Fisher and Hwy 75 | $2,800,000 | Not Selected | Constructed in 2022 under SP 6001-67 |
66 | US Hwy 71 | Resurface Hwy 71 between Itasca County line and Koochiching CR 50 | $3,645,000 | 2034 | 3610-1089743 |
66 | US Hwy 71 | Resurface Hwy 71 from south of CR 9 to south of the Beltrami/Hubbard county line | $800,000 | Not Selected | 2907-1101203 |
66 | US Hwy 71 | Resurface Hwy 71, northbound and southbound lanes from south of the Beltrami/Hubbard County line to Hwy71/Hwy 2 | $1,300,000 | Not Selected | 0409-1101190 |
65 | Hwy 34 | Resurface Hwy 34 between Hubbard County Road 4 and Akeley | $5,200,000 | Not Selected | District does not expect pavement segment to deteriorate as fast as model predicts |
64 | Hwy 11 | Recondition Hwy 11 between Williams and Lake of the Woods County Road 166 | $7,000,000 | Not Selected | Not a district priority, will continue to monitor pavement performance |
64 | Hwy 11 | Resurface Hwy 11 between Lake of the Woods County Road 166 and Baudette | $2,700,000 | Not Selected | District does not expect pavement segment to deteriorate as fast as model predicts |
64 | Hwy 11 | Resurface Hwy 11 from east of Williams to 7.6 miles west of Hwy 172 | $6,900,000 | 2033 | 3901-1123283 |
62 | Hwy 11 | Resurface Hwy 11 between Kittson Co line and Greenbush | $3,600,000 | Not Selected | District does not expect pavement segment to deteriorate as fast as model predicts |
62 | Hwy 11 | Resurface Hwy 11 between Roseau CO line and Williams | $2,000,000 | Not Selected | District does not expect pavement segment to deteriorate as fast as model predicts |
58 | Hwy 34 | Resurface Hwy 34 from Hwy 64 in Akeley to Hwy 371 in Walker | $1,700,000 | 2030 | 1105-10 |
49 | Hwy 11 | Reconstruct Hwy 11 between Roseau and Warroad | $22,300,000 | 2026, 2027 | 6803-43 |
40 | Hwy 11 | Resurface Hwy 11 between Roseau County Road 111 and Roseau County Road 15 | $4,300,000 | Not Selected | District does not expect pavement segment to deteriorate as fast as model predicts |
39 | Hwy 32 | Resurface Hwy 32 between Thief River Falls and Middle River | $7,300,000 | Not Selected | District does not expect pavement segment to deteriorate as fast as model predicts |
36 | Hwy 11 | Resurface Hwy 11 between Roseau County Road 15 and Roseau | $1,000,000 | Not Selected | District does not expect pavement segment to deteriorate as fast as model predicts |
34 | US Hwy 2 | Resurface Hwy 2 between Itasca County Road 18 and Deer River | $1,800,000 | Not Selected | Coordinating funding with another district |
33 | Hwy 11 | Resurface Hwy 11 between Hwy 32 and Roseau County Road 111 | $2,400,000 | Not Selected | District does not expect pavement segment to deteriorate as fast as model predicts |
33 | US Hwy 71 | Resurface Hwy 71 between Margie and Big Falls | $1,794,000 | Not Selected | 3611-1089723 |
28 | US Hwy 71 | Resurface Hwy 71 between Lake George and Kabekona | $3,400,000 | Not Selected | 2906-1073383 Scored in 2020. RQI forecast does not match on the ground conditions |