Urban non-freeway/non-expressway pavement projects

MnDOT District 2

Scoring criteria for urban non-freeway, non-expressway pavement projects. Out of 100 possible points, 25 points are based on the timing of the improvement, 25 points are based on cracking, rutting and patching, 10 points are based on traffic volume, 10 points are based on compliance with the Americans with Disability Act, 10 points are based on active transportation and transit, 10 points are based on other infrastructure needs, 5 points are based on the condition of local utilities under the road, and 5 points are based on whether the project will benefit an environmental justice population.

Learn more about how MnDOT evaluates and selects urban pavement projects

MnDOT scores stretches of highway based on a pavement need when selecting projects to include in the 10-year Capital Highway Investment Plan. MnDOT scores and prioritizes urban non-freeway/non-expressway pavement projects separately from the normal pavement scoring process, because of their complexity, utilities and other infrastructure and level of required local coordination and public involvement. In many instances, these roads function both as state highways and as city streets. These pavement projects can be on either National Highway System or non-NHS.

Freeways have full access control (no driveways, signals or at-grade intersections). Expressways have partial access control (limited or no driveways, few and widely spaced intersections, and may include some grade separated crossings). Both are high speed roads designed to facilitate longer trips.

For the purposes of this scoring category, MnDOT uses a flexible, context-based definition of urban. This includes areas with medium-to-high density adjacent development with small to medium setbacks and in some instances no setback. This includes both residential, industrial and commercial areas. In some instances, the urban context may cover less than a quarter mile.

Urban pavement projects are scored and selected within each district. Potential pavement projects are identified by the Highway Pavement Management Application (HPMA) and by MnDOT District staff.

Once selected, MnDOT then identifies and evaluates alternatives and other needs, legal requirements, issues and opportunities in coordination with local partners, and considers public input. In the process, non-pavement work may be added to a pavement project or a pavement project may be combined with a nearby bridge project. The department follows a context-sensitive complete streets approach, which considers the needs of all users. The final project may address a substantial number of needs beyond the pavement need that precipitated the project. Projects may move years based on local coordination, project delivery, timing of other nearby construction projects and funding shifts.

What was selected

Related links

How the projects scored

The construction costs shown on this list represent a very rough estimate based on limited information available at the time selection decisions were made. Actual construction and delivery costs will change over time as projects go from a concept through the project development process and are eventually constructed.

Last updated November 2024

Score Route  Community Description High Level Cost Estimate for Planning Purposes Year Planned (FY) Comments
84 US Hwy 71 Park Rapids Reconstruct 1-mile of Hwy 71 in Park Rapids    $8,500,000   2031 2904-20    Scored in 2019
81 US Hwy 59 Thief River Falls Resurface 2 miles of Hwy 59 in Thief River Falls    $6,000,000   2030 5705-66    
80 Hwy 1 Redby Reconstruct 1-mile of Hwy 1 in Redby    $5,800,000   2031 0404-39    Scored in 2019
80 Hwy 197 Bemidji Resurface Hwy 197 between Bemidji Ave and Hannah Ave in Bemidji   $14,000,000   2032 0416-64    
80 Hwy 197 Bemidji Resurface Hwy 197 between Hannah Ave and Gillett Drive in Bemidji    $18,000,000   2026   0416-55   
80 US Hwy 71 Menahga Resurface and sidewalk improvements on Hwy 71 in Menahga  $200,000 Not Selected Coordinating funding with another district
78 Hwy 32 Fertile Reconstruct Hwy 32 in Fertile $5,200,000 2030 6006-24
74 US75 Shelly Resurface Hwy 75 in Shelly  $200,000 Not Selected Waiting to coordinate with another project
73 US Hwy 2 Fosston Resurface and sidewalk improvements on Hwy 2 in Fosston    $7,300,000   2027   6005-74   
72 US Hwy 2B East Grand Forks Resurface and Sidewalk improvements on Hwy 2B between Demers Ave and Hwy 2 in East Grand Forks   $7,500,000   2029 6001-74    
70 US Hwy 2 Cass Lake Resurface Hwy 2 in Cass Lake   $3,800,000   2034 1102-73    
70 US Hwy 2 Crookston Resurface Hwy 2 in Crookston between Groveland Ave and the one-way pairs and Resurface Hwy 2 in Crookston from the Red Lake River Bridge to west of Fairfax Ave and Rehab the Red Lake River Bridge    $11,500,000   2034 6002-1123291    
67 Hwy 11 Karlstad Resurface Hwy 11 in Karlstad  $200,000 Not Selected Waiting to coordinate with another project
65 Hwy 197 Bemidji Resurface Hwy 197 in Bemidji between US 2 and Paul Bunyan Drive SE  $1,200,000 Not Selected District does not expect pavement segments to deteriorate as fast as the model predicts
65 Hwy 197 Bemidji Resurface Hwy 197 in Bemidji between Paul Bunyan Drive SE and 3rd Street   $1,400,000 Not Selected 2018 Construction. District does not expect pavement segments to deteriorate as fast as the model predicts
65 Hwy 32 Thief River Falls Resurface Hwy 32, Hwy 1, & Hwy 59 in Thief River Falls    $11,000,000   2034 5704-1123290    
65 Hwy 371 Hackensack Reconstruct 1 mile of Hwy 371 in Hackensack   $8,459,480   2025, 2026   1118-22   Scored in 2021
64 Hwy 371 Walker Reconstruct Hwy 371 in Walker    $20,000,000   2030-2031 1119-42    Scored in 2019
63 Hwy 34 Park Rapids Resurface Hwy 34 in Park Rapids    $4,100,000   2031 2902-46    Scored in 2019
63 US Hwy 71 Big Falls Resurface Hwy 71 in Big Falls  $100,000 Not Selected
62 Hwy 32 Red Lake Falls Resurface and sidewalk improvements on Hwy 32 in Red Lake Falls   $12,000,000   2033 6301-1055060    Scored in 2019
60 Hwy 1 Thief River Falls Reconstruct Hwy 1 in Thief River Falls between Hwy 32 and the Thief River  $300,000 Not Selected 2018 Construction. District does not expect pavement segments to deteriorate as fast as the model predicts
60 Hwy 1 Thief River Falls Resurface Hwy 1 in Thief River Falls between Brooks Avenue and Hwy 32  $200,000 Not Selected 2018 Construction. District does not expect pavement segments to deteriorate as fast as the model predicts
60 Hwy 11 Baudette Resurface Hwy 11 in Baudette between 9th Ave SE and Hwy 72  $400,000 Not Selected 2016 construction
60 US Hwy 59 Karlstad Resurface Hwy 59 in Karlstad  $500,000 Not Selected Waiting to coordinate with another project
56 Hwy 11 Roseau Resurface one mile of Hwy 11 in Roseau   $5,900,000   2025   6803-46   Scored in 2020
53 Hwy 11 Greenbush Resurface Hwy 11 in Greenbush    $2,500,000   2026   6801-19   
50 Hwy 197 Bemidji Resurface Hwy 197 in Bemidji between 3rd Street and 23rd Street  $1,000,000 Not Selected District does not expect pavement segments to deteriorate as fast as the model predicts
50 Hwy 92 Bagley Resurface Hwy 92 in Bagley  $600,000 Not Selected 2018 Construction. District does not expect pavement segments to deteriorate as fast as the model predicts
50 US Hwy 2 Crookston Improve pedestrian accessibility and safety in Crookston $6,400,000 2027 6002-76
50 US Hwy 2 Crookston Resurface Hwy 2 in Crookston between the Red Lake River and Polk CR 9  $600,000 Not Selected District does not expect pavement segments to deteriorate as fast as the model predicts
50 US Hwy 2 Bagley Resurface Hwy 2 in Bagley  $1,900,000 Not Selected 2020 Construction
50 US75 Warren Resurface and sidewalk improvements on Hwy 75 in Warren  $500,000 Not Selected 2020 Construction
48 Hwy 11 Warroad Resurface Hwy 11, improve pedestrian accessibility, add roundabouts at intersections Hwy 11/Hwy 313   $18,371,010   2025, Prior   6803-40   Selected priory to the adoption of the scoring policy
48 Hwy 11 Warroad Resurface Hwy 11 in Warroad from Elk Street to Warroad River bridge    $2,900,000   2027   6803-52   
48 Hwy 200 Halstad Resurface Hwy 200 in Halstad  $400,000 Not Selected Waiting to coordinate with another project
48 Hwy 32 Twin Valley Resurface Hwy 32 in Twin Valley  $300,000 Not Selected Waiting to coordinate with another project
40 Hwy 89 Roseau Reconstruct Hwy 89 between 7th Street and Hwy 11 in Roseau   $7,000,000   2028   6806-33   
40 US Hwy 2 East Grand Forks Resurface Hwy 2 in East Grand Forks from the ND state border and 5th Avenue NW  $1,000,000 Not Selected Waiting to coordinate with another project
40 US75 Hallock Resurface and pedestrian improvements on Hwy 75 and Hwy 175 in Hallock  $7,300,000 Not Selected 2022 Construction
40 US75 Argyle Resurface Hwy 75 in Argyle  $300,000 Not Selected
37 US75 Climax Resurface Hwy 75 in Climax  $300,000 Not Selected Waiting to coordinate with another project
35 Hwy 11 Baudette Resurface Hwy 11 in Baudette between 2nd Ave NW and 9th St SE  $500,000 Not Selected
35 Hwy 371 Cass Lake Resurface Hwy 371 in Cass Lake  $200,000 Not Selected
35 US Hwy 71 Park Rapids Resurface Hwy 71 between Hubbard CR 15 and 8th St in Park Rapids  $300,000 Not Selected
35 US75 Halstad Resurface Hwy 75 in Halstad  $300,000 Not Selected
35 US75 Hendrum Resurface Hwy 75 in Hendrum  $200,000 Not Selected
32 Hwy 200 Ada Resurface Hwy 200 in Ada  $500,000 Not Selected
25 US Hwy 2 Deer River Resurface Hwy 2 in Deer River  $200,000 Not Selected
23 Hwy 220 Climax Resurface Hwy 220 in Climax  $100,000 Not Selected
20 Hwy 72 Kelliher Resurface Hwy 72 in Kelliher  $200,000 Not Selected
20 Hwy 9 Ada Resurface Hwy 9 in Ada  $300,000 Not Selected

Score Route  Community Description High Level Cost Estimate for Planning Purposes Year Planned (FY) Comments
84 US Hwy71 Park Rapids Reconstruct 1-mile of Hwy 71 in Park Rapids    $7,800,000   2030 2904-20    Scored in 2019
81 US Hwy59 Thief River Falls Resurface 2 miles of Hwy 59 in Thief River Falls    $4,100,000   2029 5705-66    
80 Hwy 1 Redby Reconstruct 1-mile of Hwy 1 in Redby    $5,000,000   2031 0404-39    Scored in 2019
80 Hwy 197 Bemidji Resurface Hwy 197 between Bemidji Ave and Hannah Ave in Bemidji   $12,000,000   2032 0416-64    
80 Hwy 197 Bemidji Resurface Hwy 197 between Hannah Ave and Gillett Drive in Bemidji    $18,000,000   2025   0416-55   
80 US Hwy71 Menahga Resurface and sidewalk improvements on Hwy 71 in Menahga  $200,000 Not Selected Coordinating funding with another district
78 Hwy 32 Reconstruct Hwy 32 in Fertile $3,400,000   2029 6006-24    
74 Hwy 1 Northome Resurface Hwy 1 from north Jct of Hwy 71 to north Jct of Hwy 46 in Northome   $1,440,000   2028 3601-1038683    
74 US Hwy75 Shelly Resurface Hwy 75 in Shelly  $200,000 Not Selected Waiting to coordinate with another project
73 US Hwy2 Fosston Resurface and sidewalk improvements on Hwy 2 in Fosston    $7,000,000   2027   6005-74   
72 US Hwy2B East Grand Forks Resurface and Sidewalk improvements on Hwy 2B between Demers Ave and Hwy 2 in East Grand Forks   $3,500,000   2028 6001-74
70 Hwy 197 Bemidji Resurface Hwy 197, eastbound and westbound, from 23rd St to east of Hannah Ave in Bemidji   $1,100,000 2023 0416-61   
70 US Hwy2 Cass Lake Resurface Hwy 2 in Cass Lake   $3,500,000   2031 1102-1101604    Corridor under study
67 Hwy 11 Karlstad Resurface Hwy 11 in Karlstad  $200,000 Not Selected Waiting to coordinate with another project
65 Hwy 197 Bemidji Resurface Hwy 197 in Bemidji between Paul Bunyan Drive SE and 3rd Street   $1,400,000 Not Selected 2018 Construction. District does not expect pavement segments to deteriorate as fast as the model predicts
65 Hwy 197 Bemidji Resurface Hwy 197 in Bemidji between US 2 and Paul Bunyan Drive SE  $1,200,000 Not Selected District does not expect pavement segments to deteriorate as fast as the model predicts
65 Hwy 32 Thief River Falls Reconstruct Hwy 32 in Thief River Falls between Oakland Park Road and 14th Street East  $10,300,000 Not Selected Waiting to coordinate with another project
65 Hwy 371 Hackensack Reconstruct 1 mile of Hwy 371 in Hackensack   $8,000,000   2025, 2026   1118-22   Scored in 2021
64 Hwy 371 Walker Reconstruct Hwy 371 and Hwy 34 in Walker    $10,516,000   2029-2030 1119-42    Scored in 2019
64 Hwy 72 Resurface Hwy 72 between Baudette and the Canadian border   $5,164,000   2024   3905-10   Selected prior to the adoption of the selection policy.
63 Hwy 34 Park Rapids Resurface Hwy 34 in Park Rapids    $4,100,000   2030 2902-46    Scored in 2019
63 US Hwy71 Big Falls Resurface Hwy 71 in Big Falls  $100,000 Not Selected
62 Hwy 32 Red Lake Falls Resurface and sidewalk improvements on Hwy 32 in Red Lake Falls   $5,400,000   2032 6301-1055060    Scored in 2019
60 Hwy 1 Thief River Falls Reconstruct Hwy 1 in Thief River Falls between Hwy 32 and the Thief River  $300,000 Not Selected 2018 Construction. District does not expect pavement segments to deteriorate as fast as the model predicts
60 Hwy 1 Thief River Falls Resurface Hwy 1 in Thief River Falls between Brooks Avenue and Hwy 32  $200,000 Not Selected 2018 Construction. District does not expect pavement segments to deteriorate as fast as the model predicts
60 Hwy 11 Baudette Resurface Hwy 11 in Baudette between 9th Ave SE and Hwy 72  $400,000 Not Selected 2016 construction
60 US Hwy59 Karlstad Resurface Hwy 59 in Karlstad  $500,000 Not Selected Waiting to coordinate with another project
56 Hwy 11 Roseau Resurface one mile of Hwy 11 in Roseau   $5,600,000   2025   6803-46   Scored in 2020
53 Hwy 11 Greenbush Resurface Hwy 11 in Greenbush    $2,400,000   2026   6801-19   
50 Hwy 197 Bemidji Resurface Hwy 197 in Bemidji between 3rd Street and 23rd Street  $1,000,000 Not Selected District does not expect pavement segments to deteriorate as fast as the model predicts
50 Hwy 92 Bagley Resurface Hwy 92 in Bagley  $600,000 Not Selected 2018 Construction. District does not expect pavement segments to deteriorate as fast as the model predicts
50 US Hwy2 Crookston Improve pedestrian accessibility and safety in Crookston $6,400,000 2027 6002-76
50 US Hwy2 Bagley Resurface Hwy 2 in Bagley  $1,900,000 Not Selected 2020 Construction
50 US Hwy2 Crookston Resurface Hwy 2 in Crookston between the Red Lake River and Polk CR 9  $600,000 Not Selected District does not expect pavement segments to deteriorate as fast as the model predicts
50 US Hwy75 Warren Resurface and sidewalk improvements on Hwy 75 in Warren  $500,000 Not Selected 2020 Construction
48 Hwy 11 Warroad Resurface Hwy 11, improve pedestrian accessibility, add roundabouts at intersections Hwy 11/Hwy 313   $16,900,000   2024, 2025   6803-40   Selected priory to the adoption of the scoring policy
48 Hwy 200 Halstad Resurface Hwy 200 in Halstad  $400,000 Not Selected Waiting to coordinate with another project
48 Hwy 32 Twin Valley Resurface Hwy 32 in Twin Valley  $300,000 Not Selected Waiting to coordinate with another project
40 Hwy 89 Roseau Reconstruct Hwy 89 between 7th Street and Hwy 11 in Roseau   $6,100,000   2028 6806-33    
40 US Hwy2 East Grand Forks Resurface Hwy 2 in East Grand Forks from the ND state border and 5th Avenue NW  $1,000,000 Not Selected Waiting to coordinate with another project
40 US Hwy75 Hallock Resurface and pedestrian improvements on Hwy 75 and Hwy 175 in Hallock  $7,300,000 Not Selected 2022 Construction
40 US Hwy75 Argyle Resurface Hwy 75 in Argyle  $300,000 Not Selected
37 US Hwy75 Climax Resurface Hwy 75 in Climax  $300,000 Not Selected Waiting to coordinate with another project
35 Hwy 11 Baudette Resurface Hwy 11 in Baudette between 2nd Ave NW and 9th St SE  $500,000 Not Selected
35 Hwy 371 Cass Lake Resurface Hwy 371 in Cass Lake  $200,000 Not Selected Recently reconstructed
35 US Hwy71 Park Rapids Resurface Hwy 71 between Hubbard CR 15 and 8th St in Park Rapids  $300,000 Not Selected
35 US Hwy75 Halstad Resurface Hwy 75 in Halstad  $300,000 Not Selected
35 US Hwy75 Hendrum Resurface Hwy 75 in Hendrum  $200,000 Not Selected
32 Hwy 200 Ada Resurface Hwy 200 in Ada  $500,000 Not Selected
25 US Hwy2 Deer River Resurface Hwy 2 in Deer River  $200,000 Not Selected
23 Hwy 220 Climax Resurface Hwy 220 in Climax  $100,000 Not Selected
20 Hwy 72 Kelliher Resurface Hwy 72 in Kelliher  $200,000 Not Selected
20 Hwy 9 Ada Resurface Hwy 9 in Ada  $300,000 Not Selected

Score Route  Community Description High Level Cost Estimate for Planning Purposes Year Planned (FY) Comments
84 US Hwy 71 Park Rapids Reconstruct 1-mile of Hwy 71 in Park Rapids    $7,800,000   2029 2904-20    Scored in 2019
81 US Hwy 59 Thief River Falls Resurface 2 miles of Hwy 59 in Thief River Falls    $4,100,000   2029 5705-1038697    
80 Hwy 197 Bemidji Resurface Hwy 197 between Bemidji Ave and Gillett Drive in Bemidji    $5,100,000   2028 0416-55    Scored in 2019
80 Hwy 1 Redby Reconstruct 1-mile of Hwy 1 in Redby    $5,300,000   2031 0404-39    Scored in 2019
80 US Hwy 71 Menahga Resurface and sidewalk improvements on Hwy 71 in Menahga  $200,000 Not Selected Coordinating funding with another district
74 Hwy 1 Northome Resurface Hwy 1 from north Jct of Hwy 71 to north Jct of Hwy 46 in Northome   $1,440,000   2028 3601-1038683    
74 US75 Shelly Resurface Hwy 75 in Shelly  $200,000 Not Selected Waiting to coordinate with another project
73 US Hwy 2 Fosston Resurface and sidewalk improvements on Hwy 2 in Fosston    $2,100,000   2027 6005-74    
72 US Hwy 2B East Grand Forks Resurface and Sidewalk improvements on Hwy 2B between the Sorlie Bridge and Hwy 2 in East Grand Forks   $3,500,000   2028 6001-74    
70 US Hwy 2 Cass Lake Resurface Hwy 2 in Cass Lake   $3,500,000   2032 1102-1101604    Corridor under study
67 Hwy 11 Karlstad Resurface Hwy 11 in Karlstad  $200,000 Not Selected Waiting to coordinate with another project
65 Hwy 371 Hackensack Reconstruct 1 mile of Hwy 371 in Hackensack   $6,200,000   2025   1118-22  Scored in 2021
65 Hwy 197 Bemidji Resurface Hwy 197 in Bemidji between Paul Bunyan Drive SE and 3rd Street   $1,400,000 Not Selected 2018 Construction. District does not expect pavement segments to deteriorate as fast as the model predicts
65 Hwy 197 Bemidji Resurface Hwy 197 in Bemidji between US 2 and Paul Bunyan Drive SE  $1,200,000 Not Selected District does not expect pavement segments to deteriorate as fast as the model predicts
65 Hwy 32 Thief River Falls Reconstruct Hwy 32 in Thief River Falls between Oakland Park Road and 14th Street East  $10,300,000 Not Selected Waiting to coordinate with another project
64 Hwy 371 Walker Reconstruct Hwy 371 and Hwy 34 in Walker    $9,700,000   2029 1119-42   Scored in 2019
63 Hwy 34 Park Rapids Resurface Hwy 34 in Park Rapids    $4,100,000   2029 2902-46    Scored in 2019
63 US Hwy 71 Big Falls Resurface Hwy 71 in Big Falls  $100,000 Not Selected
62 Hwy 32 Red Lake Falls Resurface and sidewalk improvements on Hwy 32 in Red Lake Falls   $5,400,000   2031 6301-1055060    Scored in 2019
60 Hwy 1 Thief River Falls Reconstruct Hwy 1 in Thief River Falls between Hwy 32 and the Thief River  $300,000 Not Selected 2018 Construction. District does not expect pavement segments to deteriorate as fast as the model predicts
60 Hwy 1 Thief River Falls Resurface Hwy 1 in Thief River Falls between Brooks Avenue and Hwy 32  $200,000 Not Selected 2018 Construction. District does not expect pavement segments to deteriorate as fast as the model predicts
60 Hwy 11 Baudette Resurface Hwy 11 in Baudette between 9th Ave SE and Hwy 72  $400,000 Not Selected 2016 construction
60 US Hwy 59 Karlstad Resurface Hwy 59 in Karlstad  $500,000 Not Selected Waiting to coordinate with another project
56 Hwy 11 Roseau Resurface one mile of Hwy 11 in Roseau   $4,900,000   2025   6803-46   Scored in 2020
53 Hwy 11 Greenbush Resurface Hwy 11 in Greenbush    $1,900,000   2026   6801-19   
50 US Hwy 2 Crookston Improve pedestrian accessibility and safety in Crookston $6,400,000 2025 6002-76
50 Hwy 197 Bemidji Resurface Hwy 197 in Bemidji between 3rd Street and 23rd Street  $1,000,000 Not Selected District does not expect pavement segments to deteriorate as fast as the model predicts
50 Hwy 92 Bagley Resurface Hwy 92 in Bagley  $600,000 Not Selected 2018 Construction. District does not expect pavement segments to deteriorate as fast as the model predicts
50 US Hwy 2 Bagley Resurface Hwy 2 in Bagley  $1,900,000 Not Selected 2020 Construction
50 US Hwy 2 Crookston Resurface Hwy 2 in Crookston between the Red Lake River and Polk CR 9  $600,000 Not Selected District does not expect pavement segments to deteriorate as fast as the model predicts
50 US75 Warren Resurface and sidewalk improvements on Hwy 75 in Warren  $500,000 Not Selected 2020 Construction
48 Hwy 11 Warroad Resurface Hwy 11, improve pedestrian accessibility, add roundabouts at intersections Hwy 11/Hwy 313 and Hwy 11/Lake Street in Warroad    $13,200,000   2023, 2024   6803-40   Selected priory to the adoption of the scoring policy
48 Hwy 200 Halstad Resurface Hwy 200 in Halstad  $400,000 Not Selected Waiting to coordinate with another project
48 Hwy 32 Twin Valley Resurface Hwy 32 in Twin Valley  $300,000 Not Selected Waiting to coordinate with another project
40 Hwy 89 Roseau Reconstruct Hwy 89 between 7th Street and Hwy 11 in Roseau   $4,200,000   2028 6806-33    
40 US Hwy 2 East Grand Forks Resurface Hwy 2 in East Grand Forks from the ND state border and 5th Avenue NW  $1,000,000 Not Selected Waiting to coordinate with another project
40 US75 Hallock Resurface and pedestrian improvements on Hwy 75 and Hwy 175 in Hallock  $7,300,000 Not Selected 2022 Construction
40 US75 Argyle Resurface Hwy 75 in Argyle  $300,000 Not Selected
37 US75 Climax Resurface Hwy 75 in Climax  $300,000 Not Selected Waiting to coordinate with another project
35 Hwy 11 Baudette Resurface Hwy 11 in Baudette between 2nd Ave NW and 9th St SE  $500,000 Not Selected District does not expect pavement segment to deteriorate as fast as model predicts 
35 Hwy 371 Cass Lake Resurface Hwy 371 in Cass Lake  $200,000 Not Selected Roadway was recently reconstructed
35 US Hwy 71 Park Rapids Resurface Hwy 71 between Hubbard CR 15 and 8th St in Park Rapids  $300,000 Not Selected
35 US75 Halstad Resurface Hwy 75 in Halstad  $300,000 Not Selected
35 US75 Hendrum Resurface Hwy 75 in Hendrum  $200,000 Not Selected
32 Hwy 200 Ada Resurface Hwy 200 in Ada  $500,000 Not Selected
25 US Hwy 2 Deer River Resurface Hwy 2 in Deer River  $200,000 Not Selected
23 Hwy 220 Climax Resurface Hwy 220 in Climax  $100,000 Not Selected
20 Hwy 72 Kelliher Resurface Hwy 72 in Kelliher  $200,000 Not Selected Roadway was recently reconstructed
20 Hwy 9 Ada Resurface Hwy 9 in Ada  $300,000 Not Selected Roadway was recently reconstructed

 

View more detailed scores (Excel).

Score Route  Community Description  High-Level Cost Estimate for Planning Purposes  Year Planned (FY) Comments
84 US Hwy 71 Park Rapids Reconstruct 1-mile of Hwy 71 in Park Rapids  $7,400,000 2029 2904-1038222 Scored in 2019
81 US Hwy 59 Thief River Falls Resurface 2 miles of Hwy 59 in Thief River Falls  $8,700,000 2029 5705-1038697 Scored in 2019
80 US Hwy 71 Menahga Resurface and sidewalk improvements on Hwy 71 in Menahga  $200,000 Not Selected Coordinating funding with another district
80 Hwy 197 Bemidji Resurface Hwy 197 between Bemidji Ave and Hwy 71 in Bemidji  $2,000,000 2028 SP 0416-55. Scored in 2019
80 Hwy 1 Redby Reconstruct 1-mile of Hwy 1 in Redby  $4,800,000 2030 SP 0404-39 Scored in 2019
79 US75 Donaldson Reconstruct Hwy 75 in Donaldson  $2,100,000 2029 SP 3509-29 Tied to a rural pavement project
78 Hwy 46 Northome Reconstruct Hwy 46 in Northome  $2,600,000 2028 3109-47 Tied to a rural pavement project
78 Hwy 223 Leonard Resurface and sidewalk improvements on Hwy 223 in Leonard  $100,000 2024 SP 1508-08 Tied to a rural pavement project
74 US75 Shelly Resurface Hwy 75 in Shelly  $200,000 Not Selected Waiting to coordinate with another project
73 US Hwy 2 Fosston Resurface and sidewalk improvements on Hwy 2 in Fosston  $1,200,000 2027 6005-1038943
72 US Hwy 2B East Grand Forks Recondition and Sidewalk improvements on Hwy 2B between the Red River and Hwy 2 in East Grand Forks  $1,300,000 2028 6001-1089323
72 Hwy 220 Alvarado Resurface and sidewalk improvements on Hwy 220 in Alvarado  $200,000 2029 6017-1089345 Tied to a rural pavement project
70 US Hwy 2 Cass Lake Reconstruct Hwy 2 in Cass Lake between Hwy 371 and the end of the 4-lane  $12,900,000 Not Selected Corridor under study
70 US75 Kennedy Reconstruct Hwy 75 in Kennedy  $3,000,000 2029 SP 3509-29 Tied to a rural pavement project
67 Hwy 11 Karlstad Resurface Hwy 11 in Karlstad  $200,000 Not Selected Waiting to coordinate with another project
65 Hwy 32 Thief River Falls Reconstruct Hwy 32 in Thief River Falls between Oakland Park Road and 14th Street East  $10,300,000 Not Selected Waiting to coordinate with another project
65 Hwy 197 Bemidji Resurface Hwy 197 in Bemidji between US 2 and Paul Bunyan Drive SE  $1,200,000 Not Selected District does not expect pavement segments to deteriorate as fast as the model predicts
65 Hwy 197 Bemidji Resurface Hwy 197 in Bemidji between Paul Bunyan Drive SE and 3rd Street   $1,400,000 Not Selected 2018 Construction. District does not expect pavement segments to deteriorate as fast as the model predicts
65 Hwy 200 Laporte Reconstruct Hwy 200 in Laporte  $2,600,000 2026 SP 2908-31. Tied to a rural pavement project
64 Hwy 371 Walker Reconstruct Hwy 371 between Park Entrance and Hwy 34 in Walker  $6,500,000 2028 1119-42  Scored in 2019
64 Hwy 72 Baudette Recondition Hwy 72 between Baudette and the Canadian border  $2,900,000 2023 SP 3905-10 Scored prior to the adoption of the selection policy.
64 Hwy 371 Hackensack Reconstruct 1 mile of Hwy 371 in Hackensack  $4,700,000 2025 SP 1118-22 Scored in 2019
63 US Hwy 71 Big Falls Resurface Hwy 71 in Big Falls  $100,000 Not Selected  
63 Hwy 34 Park Rapids Resurface Hwy 34 in Park Rapids  $3,400,000 2029 2902-1037840 Scored in 2019
62 Hwy 32 Red Lake Falls Resurface and sidewalk improvements on Hwy 32 in Red Lake Falls  $800,000 2030 6301-1055060 Scored in 2019
60 Hwy 1 Thief River Falls Resurface Hwy 1 in Thief River Falls between Brooks Avenue and Hwy 32  $200,000 Not Selected 2018 Construction. District does not expect pavement segments to deteriorate as fast as the model predicts
60 Hwy 1 Thief River Falls Reconstruct Hwy 1 in Thief River Falls between Hwy 32 and the Thief River  $300,000 Not Selected 2018 Construction. District does not expect pavement segments to deteriorate as fast as the model predicts
60 Hwy 11 Baudette Resurface Hwy 11 in Baudette between 9th Ave SE and Hwy 72  $400,000 Not Selected 2016 construction
60 US Hwy 59 Karlstad Resurface Hwy 59 in Karlstad  $500,000 Not Selected Waiting to coordinate with another project
60 Hwy 92 Clearbrook Reconstruct Hwy 92 in Clearbrook  $1,500,000 2027 SP 1507-68 Scored in 2019
56 Hwy 11 Roseau Resurface one mile of Hwy 11 in Roseau  $500,000 2024 SP 6803-46 Scored in 2020
53 Hwy 11 Greenbush Reconstruct Hwy 11 in Greenbush  $2,100,000 2026 SP 6801-19
53 US Hwy 59 Lake Bronson Recondition and sidewalk improvements on Hwy 59 in Lake Bronson  $200,000 2026 SP3506-27 Tied to a rural pavement project
50 US Hwy 2 Bagley Resurface Hwy 2 in Bagley  $1,900,000 Not Selected 2020 Construction
50 US Hwy 2 Crookston Resurface Hwy 2 in Crookston between the Red Lake River and Polk CR 9  $600,000 Not Selected District does not expect pavement segments to deteriorate as fast as the model predicts
50 US75 Warren Resurface and sidewalk improvements on Hwy 75 in Warren  $500,000 Not Selected 2020 Construction
50 Hwy 92 Bagley Resurface Hwy 92 in Bagley  $600,000 Not Selected 2018 Construction. District does not expect pavement segments to deteriorate as fast as the model predicts
50 Hwy 197 Bemidji Resurface Hwy 197 in Bemidji between 3rd Street and 23rd Street  $1,000,000 Not Selected District does not expect pavement segments to deteriorate as fast as the model predicts
50 US Hwy 2 Crookston Resurface Hwy 2 in Crookston between Groveland Avenue and the Red Lake River  $1,400,000 2024 SP 6002-76
48 Hwy 11 Warroad Resurface Hwy 11, improve pedestrian accessibility, add roundabouts at intersections Hwy 11/Hwy 313 and Hwy 11/Lake Street in Warroad  $8,600,000 2024 SP 6803-40. Selected priory to the adoption of the scoring policy
48 Hwy 32 Fertile Reconstruct Hwy 32 in Fertile  $4,800,000 2028 6007-1038990 Tied to a rural pavement project
48 Hwy 32 Twin Valley Resurface Hwy 32 in Twin Valley  $300,000 Not Selected Waiting to coordinate with another project
48 Hwy 200 Halstad Resurface Hwy 200 in Halstad  $400,000 Not Selected Waiting to coordinate with another project
42 Hwy 89 Grygla Resurface Hwy 89 and pedestrian improvements between Marshall CR 54 and Grygla  $300,000 2024 4508-34
40 US Hwy 2 East Grand Forks Resurface Hwy 2 in East Grand Forks from the ND state border and 5th Avenue NW  $1,000,000 Not Selected Waiting to coordinate with another project
40 US75 Argyle Resurface Hwy 75 in Argyle  $300,000 Not Selected
40 Hwy 89 Roseau Reconstruct Hwy 89 between 7th Street and Hwy 11 in Roseau  $3,700,000 2027 6806-33
40 US75 Hallock Resurface and pedestrian improvements on Hwy 75 and Hwy 175 in Hallock  $7,300,000 2023 Selected prior to the adoption of the scoring policy. 3509-26
37 US75 Climax Resurface Hwy 75 in Climax  $300,000 Not Selected Waiting to coordinate with another project
35 US Hwy 71 Park Rapids Resurface Hwy 71 between Hubbard CR 15 and 8th St in Park Rapids  $300,000 Not Selected
35 Hwy 11 Baudette Resurface Hwy 11 in Baudette between 2nd Ave NW and 9th St SE  $500,000 Not Selected
35 US75 Hendrum Resurface Hwy 75 in Hendrum  $200,000 Not Selected
35 US75 Halstad Resurface Hwy 75 in Halstad  $300,000 Not Selected
35 Hwy 371 Cass Lake Resurface Hwy 371 in Cass Lake  $200,000 Not Selected
32 Hwy 200 Ada Resurface Hwy 200 in Ada  $500,000 Not Selected
28 Hwy 1 Northome Resurface Hwy 1 between 5th Street and Hwy 46 in Northome  $100,000 Not Selected
25 Hwy 34 Akeley Reconstruct Hwy 34 in Akeley  $4,100,000 2023 SP 2902-44. Selected prior to the adoption of the scoring policy
25 US75 Nielsville Sidewalk improvements on Hwy 75 in Nielsville  $100,000 2022 DBE contractor to perform sidewalk work
25 US Hwy 2 Deer River Resurface Hwy 2 in Deer River  $200,000 Not Selected
23 Hwy 220 Climax Resurface Hwy 220 in Climax  $100,000 Not Selected  
20 Hwy 9 Ada Resurface Hwy 9 in Ada  $300,000 Not Selected
20 Hwy 72 Kelliher Resurface Hwy 72 in Kelliher  $200,000 Not Selected
18 US Hwy 2 Mcintosh Reconstruct Hwy 2 in McIntosh  $8,400,000 2022 SP 6005-68 Selected prior to the adoption of the selection policy

Score Route  Community Description  High-Level Cost Estimate for Planning Purposes  Year Planned (FY) Comments
92 Hwy 197 Bemidji Resurface Hwy 197 in Bemidji from 23rd Street to Hwy 71 $6,700,000 2027  
87 US 2B East Grand Forks Resurface Hwy 2B in East Grand Forks from the Sorlie Bridge to Hwy 2 $800,000 Not Selected  Corridor under study (downtown East Grand Forks)
84 US 71 Park Rapids Reconstruct Hwy 71 in Park Rapids from the south city limits to Main Ave $4,300,000 2029  
80 US 2 Cass Lake Resurface Hwy 2 in Cass Lake from Hwy 371 to the end of the 4-lane $1,000,000 Not Selected  Corridor under study
80 US 59 Thief River Falls Reconstruct Hwy 59 in Thief River Falls from 155th Street to 1st Street $4,300,000 2027  
76 Hwy 1 Thief River Falls Reconstruct Hwy 1 in Thief River Falls from Hwy 32 to the Thief River $1,900,000 Not Selected  Received new wearing course in 2018
76 Hwy 371 Walker Resurface Hwy 371 in Walker $300,000 2027 Tied to another paving project
75 US 2 Fosston Resurface Hwy 2 in Fosston from Polk County Road 30 to the east city limits $1,400,000 2030 Corridor under study
75 Hwy 72 Baudette Reconstruct Hwy 72 from Hwy 11 to the Border Crossing Station $2,400,000 2022  
75 Hwy 197 Bemidji Resurface Hwy 197 in Bemidji from Paul Bunyan Drive SE to 3rd Street  $1,400,000 Not Selected  Waiting to coordinate with another project
74 US 75 Donaldson Reconstruct Hwy 75 in Donaldson $900,000 2027 Tied to rural paving project
73 US 59 Thief River Falls Reconstruct Hwy 59 in Thief River Falls from 1st Street to Atlantic Avenue $900,000 Not Selected  District does not expect pavement segments to deteriorate as fast as the model predicts
73 Hwy 220 Alvarado Resurface Hwy 220 from East Grand Forks to Hwy 1 in Alvarado $100,000 2027 Tied to rural paving project
72 Hwy 1 Thief River Falls Resurface Hwy 1 in Thief River Falls from Brooks Avenue to Hwy 32 $100,000 Not Selected  Received new wearing course in 2018
71 US 2 McIntosh Reconstruct Hwy 2 in McIntosh $9,400,000 Not Selected  Waiting to coordinate with another project
71 Hwy 32 Fertile Reconstruct Hwy 32 in Fertile  $2,700,000 Not Selected  Waiting to coordinate with another project
70 Hwy 371 Hackensack Reconstruct Hwy 371 in Hackensack $2,500,000 2025 Selected prior to policy (in 2019-2029 CHIP)
69 US 2 Crookston Resurface Hwy 2 in Crookston from Hwy 75 to Groveland Avenue $1,100,000 Not Selected  Waiting to coordinate with another project
66 US 75 Halstad Reconstruct Hwy 75 in Halstad $3,600,000 Not Selected  Received new wearing course in 2019
66 US 75 Kennedy Reconstruct Hwy 75 in Kennedy $1,500,000 2027 Tied to rural paving project
65 US 2 Crookston Resurface Hwy 2 in Crookston from Groveland Avenue to the Red Lake River $2,000,000 Not Selected  Waiting to coordinate with another project
65 US 59 Karlstad Resurface Hwy 59 in Karlstad $300,000 Not Selected  Waiting to coordinate with another project
65 Hwy 197 Bemidji Resurface Hwy 197 in Bemidji from 3rd Street to 23rd Street $1,000,000 Not Selected  Waiting to coordinate with another project
63 Hwy 11 Karlstad Resurface Hwy 11 in Karlstad $100,000 Not Selected  Waiting to coordinate with another project
62 Hwy 32 Red Lake Falls Resurface Hwy 32 in Red Lake Falls $400,000 2029 Tied to rural paving project
60 Hwy 32 Twin Valley Resurface Hwy 32 in Twin Valley $100,000 Not Selected  Waiting to coordinate with another project
58 Hwy 1 Northome Reconstruct Hwy 1 from 5th Street to Hwy 46 in Northome $1,000,000 Not Selected  Received new wearing course in 2019
57 Hwy 34 Park Rapids Resurface Hwy 34 in Park Rapids from Western Avenue to Hubbard County Road 4 $1,200,000 2029  
55 Hwy 11 Roseau Resurface Hwy 11 in Roseau from 4th Ave NW to Roseau County Road 124 $300,000 2024 Selected prior to policy (in 2019-2029 CHIP)
55 Hwy 32 Thief River Falls Resurface Hwy 32 in Thief River Falls from Oakland Park Road to 14th Street East $300,000 Not Selected  Waiting to coordinate with another project
53 Hwy 11 Roseau Reconstruct Hwy 11 in Greenbush $3,000,000 2026 Selected prior to policy (in 2019-2022 STIP)
52 US 59 Winger Resurface Hwy 59 in Winger $300,000 Not Selected  Waiting to coordinate with another project
52 Hwy 89 Grygla Resurface Hwy 89 in Grygla $200,000 2024 Tied to rural paving project
51 Hwy 1 Thief River Falls Reconstruct Hwy 1 in Thief River Falls from the Thief River to Pennington County Road 18 $2,300,000 Not Selected  Received new wearing course in 2018
48 Hwy 197 Bemidji Resurface Hwy 197 in Bemidji from Hwy 2 to Paul Bunyan Drive SE $1,200,000 Not Selected  Waiting to coordinate with another project
48 Hwy 220 East Grand Forks Reconstruct Hwy 220 in East Grand Forks from Hwy 2 to Polk County Road 19 $8,800,000 Not Selected  Alternatives that may include local partner participation need to be further refined
47 Hwy 200 Halstad Resurface Hwy 200 in Halstad $200,000 Not Selected  Waiting to coordinate with another project
45 US 2 East Grand Forks Resurface Hwy 2 in East Grand Forks from the ND state border to 5th Avenue NW $1,000,000 Not Selected  Waiting to coordinate with another project
45 US 71 Big Falls Resurface Hwy 71 in Big Falls $100,000 Not Selected  Waiting to coordinate with another project
43 Hwy 34 Akeley Reconstruct Hwy 34 in Akeley $1,000,000 2023 Selected prior to policy (in 2019-2022 STIP)
41 Hwy 175 Hallock Partial Reconstruct of Hwy 175 in Hallock $1,600,000 2022 Selected prior to policy (in 2019-2022 STIP)
34 Hwy 200 Ada Resurface Hwy 200 in Ada $300,000 Not Selected   
29 Hwy 11 Baudette Resurface Hwy 11 in Baudette from 2nd Street NW to 9th Avenue SE $300,000 Not Selected   
29 Hwy 92 Bagley Resurface Hwy 92 in Bagley $100,000 Not Selected   
27 US 75 Hallock Partial Reconstruct of Hwy 75 in Hallock $2,200,000 2022 Selected prior to policy (in 2019-2022 STIP)
23 US 2 Crookston Resurface Hwy 2 in Crookston from the Red Lake River to Polk County Road 9 $300,000 Not Selected   
23 Hwy 220 Climax Resurface Hwy 220 in Climax $100,000 Not Selected   
21 Hwy 9 Ada Resurface Hwy 9 in Ada $200,000 Not Selected   
21 Hwy 72 Kelliher Resurface Hwy 72 in Kelliher $100,000 Not Selected   

 

Score Community Route Description  High level construction cost estimate for planning purposes  Year Planned (FY) Comments
84 Park Rapids US Hwy 71 Reconstruction from the south city limits to Main Ave  $9,400,000 2028  
84 Thief River Falls US Hwy 59 Medium mill and overlay from Atlantic Ave to Highway 32 $300,000 Not selected Waiting to coordinate with another project
82 East Grand Forks US Hwy 2B Medium mill and overlay from the Sorlie Bridge to Highway 2 $1,500,000 Not selected Currently negotiating in jurisdictional transfer
81 Thief River Falls US Hwy 59 Reconstruction from 155th St and 1st St $5,400,000 2027  
81 Thief River Falls Hwy 32 Thick mill and overlay from Oakland Park Rd to 14th St E $1,100,000 Not selected Waiting to coordinate with another project
80 Baudette Hwy 72 Reconstruction from Highway 11 to the US/Canada border $2,700,000 2022  
80 Bemidji Hwy 197 Reconstruction from Highway 71 to Highway 2 $19,000,000 2026  
80 Redby Hwy 1 Reconstruction in Redby $4,600,000 2029  
76 Warroad Hwy 11 Reconstruction from Highway 313 to Roseau County Road 5 $11,000,000 Not selected Waiting to coordinate with another project
74 Humboldt  US75 Reconstruction in Humboldt  $1,600,000 Not selected Waiting to coordinate with another project
73 Donaldson US75 Reconstruction in Donaldson  $15,000,000 2024 Coordinated with larger pavement project
73 Fosston US Hwy 2 Medium mill and overlay from Polk County Road 30 to Fosston city limits $1,400,000 2029  
71 Fertile Hwy 32 Reconstruction in Fertile $5,300,000 Not selected
71 Mcintosh  US Hwy 2 Reconstruction in McIntosh  $19,000,000 Not selected
70 Bemidji Hwy 197 Medium mill and overlay from Paul Bunyan Dr SE to 3rd St $1,400,000 Not selected
70 Bemidji Hwy 197 Thin mill and overlay from 3rd St to 23rd St $1,000,000 Not selected
70 Clearbrook Hwy 92 Reclaim and overlay in Clearbrook $300,000 Not selected
68 Crookston US Hwy 2 Thin mill and overlay from Highway 75 to Groveland Ave $1,400,000 Not selected
68 Lake Bronson  US Hwy 59 Reconstruction in Lake Bronson  $1,300,000 Not selected
66 Karlstad US Hwy 59 Medium mill and overlay in Karlstad $500,000 Not selected
65 Kennedy US75 Reconstruction in Kennedy  $4,100,000 2024 Coordinated with larger pavement project
65 Crookston US Hwy 2 Major Concrete pavement rehabilitation/diamond grinding from Groveland Avenue to the Red Lake River $1,500,000 Not selected
63 Park Rapids Hwy 34 Thin mill and overlay from Western Ave to Hubbard County Road 4 $5,900,000 2028 Selected prior to policy (in 2019-2028 CHIP)
63 Karlstad Hwy 11 Medium mill and overlay in Karlstad $200,000 Not selected
62 Red Lake Falls Hwy 32 Medium mill an overlay in Red Lake Falls $8,200,000 2029 Selected prior to policy (in 2019-2028 CHIP)
61 Newfolden US Hwy 59 Resurface in Newfolden $200,000 Not selected
60 East Grand Forks US Hwy 2 Major concrete pavement rehabilitation from the North Dakota state border to 5th Avenue NW $300,000 Not selected
56 Roseau Hwy 11 Medium mill and overlay from 4th Ave NW to Roseau County Road 124 $500,000 2024 Selected prior to policy (in 2019-2028 CHIP)
56 Shevlin US Hwy 2 Medium mill and overlay in Shevlin  $900,000 Not selected
56 Solway US Hwy 2 Medium mill and overlay in Solway $800,000 Not selected
55 Grygla Hwy 89 Medium mill and overlay in Grygla $300,000 2025 Selected prior to policy (in 2019-2028 CHIP)
55 Thief River Falls US Hwy 59 Reconstruction from 1st St to Atlantic Ave $5,000,000 Not selected
53 Greenbush Hwy 11 Reconstruction in Greenbush $1,900,000 2026 Selected prior to policy (in 2019-2028 CHIP)
51 Thief River Falls Hwy 1 Reconstruction from Highway 59 to Atlantic Ave $4,500,000 2020 Selected prior to policy (in 2019-2022 STIP)
49 Laporte Hwy 200 Reconstruction in Laporte $2,900,000 2025 Coordinated with a larger pavement project
48 Alvarado  Hwy 220 Thin mill and overlay in Alvarado $100,000 Not selected
47 Bemidji Hwy 197 Reconstruction from Bemidji Ave to Highway 2 $19,000,000 2026 Selected prior to policy (in 2019-2028 CHIP)
47 Halstad Hwy 200 Major concrete rehabilitation/diamond grinding in Halstad $500,000 Not selected
44 Climax US75 Minor concrete rehabilitation and diamond grinding in Climax $200,000 Not selected
44 Bagley  Hwy 92 Thin mill and overlay in Bagley $300,000 Not selected
43 Bemidji Hwy 197 Thin mill and overlay from Highway 2 to Paul Bunyan Dr SE $1,200,000 Not selected
43 East Grand Forks Hwy 220 Reconstruction from Highway 2 to Polk County Road 19 $12,000,000 Not selected
43 Crookston US Hwy 2 Major concrete pavement rehabilitation from the Red Lake River to Polk County Road 9 $1,500,000 Not selected
42 Warren US75 Medium mill and overlay in Warren $300,000 2020 Selected prior to policy (in 2019-2022 STIP)
42 Red Lake Hwy 1 Reconstruction in Red Lake $10,000,000 2020 Selected prior to policy (in 2019-2022 STIP)
41 Hallock US75/Hwy 175 Thin mill and overlay in Hallock $400,000 Not selected
38 Nielsville US75 Minor concrete rehabilitation and diamond grinding in Nielsville $200,000 Not selected
37 Winger US Hwy 59 Thin mill and overlay in Winger $400,000 2021 Selected prior to policy (in 2019-2022 STIP)
37 Baudette Hwy 11 Thin mill and overlay from 2nd St NW to 9th Ave SE $500,000 Not selected
36 Bagley  US Hwy 2 Thin mill and overlay in Bagley $1,900,000 2020 Selected prior to policy (in 2019-2022 STIP)
35 Twin Valley  Hwy 32 Thin mill and overlay in Twin Valley $300,000 Not selected
34 Ada Hwy 200 Minor concrete rehabilitation/diamond grinding in Ada $500,000 Not selected
32 Warren Hwy 1 Medium mill and overlay  in Warren $400,000 2020 Selected prior to policy (in 2019-2022 STIP)
32 Akeley Hwy 34 Reconstruction in Akeley $4,900,000 2022 Selected prior to policy (in 2019-2022 STIP)
30 Lancaster  US Hwy 59 Medium mill and overlay in Lancaster $200,000 Not selected
26 Argyle US75 Thin mill and overlay in Argyle $300,000 2020 Selected prior to policy (in 2019-2022 STIP)
25 St. Hillaire Hwy 32 Thin mill and overlay in St. Hillaire $900,000 2020 Selected prior to policy (in 2019-2022 STIP)
23 Climax Hwy 220 Minor concrete rehabilitation in Climax $100,000 Not selected